COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 29-Apr-2024

Vegetative Plantings - West Hackberry Planting Demo COMPLETE

PROJECT DATA

PROJECT: Vegetative Plantings - West Hackberry Planting Demo COMPLETE
PRIORITY LIST: 1 PROJECT NO: 0107-1 CWPPRA NO: FCS-19 DNR NO: CS-19
PROJECT TYPE: Vegetative Plantings NET ACRES BENEFITTED: 0
REGION: 4 BASIN: Calcasieu/Sabine PARISH: Cameron
LEAD AGENCY: NRCS
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA.

MILESTONES:

CSA EXECUTION: 17-Apr-1993 ( Actual )    
DESIGN COMPLETION: 30-Mar-1993 ( Actual )    
CONSTRUCTION START: 15-Apr-1993 ( Actual )    
CONSTRUCTION COMPLETION: 30-Mar-1994 ( Actual )    
ESCROW AMENDMENT 25-Aug-1993 ( Actual ) No: 0
MONITORING PLAN APPROVAL: 21-Sep-1995 ( Actual )    
O and M PLAN APPROVAL:    
DEAUTHORIZATION DATE:      
CASH FLOW PROECTS:        
Phase 1 Approval: 31-Oct-1991 ( Actual )    
Phase 2 Approval:    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT: 3 Charles W. Boustany
STATE SENATE DISTRICT: 25 Dan "Blade" Morrish
STATE HOUSE DISTRICT: 36 Chuck Kleckley

Point of Contact:

DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE

Quin Kinler



Denham Springs, LA 
PHONES:  
Office:
Fax:

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 29-Apr-2024

Vegetative Plantings - West Hackberry Planting Demo COMPLETE

PROJECT LOCATION:

PROJECT DESCRIPTION:

Vegetative Plantings will consist of planting smooth cordgrass and protecting it with wave-stilling fences.

PROJECT STATUS: (Project Status Last Updated: 01-Jan-1990 )

Sub-project of the Vegetative Plantings project. Complete.

FUND STATUS:

The current project estimate is $256,251 , which includes $162,974 for construction first costs, and $80,228 and $13,048 for 20 years of monitoring and operations and maintenance, respectively.

LaCoast.gov Project Managers' Technical Factsheet