PROJECT STATUS REPORT as of 18-Jun-2013
PROJECT DATA
| PROJECT: Alligator Bend Marsh Restoration and Shoreline Protection |
| PRIORITY LIST: 16 | PROJECT NO: 1601 | CWPPRA NO: PO-34 | DNR NO: PO-34 |
| PROJECT TYPE: Marsh Creation | NET ACRES BENEFITTED: 192 |
| REGION: 1 | BASIN: Pontchartrain | PARISH: Orleans |
| LEAD AGENCY: NRCS |
| LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA |
MILESTONES:
| CSA EXECUTION: | 11-Jun-2008 | ( Actual ) | ||
| DESIGN COMPLETION: | 15-Nov-2011 | ( Actual ) | ||
| CONSTRUCTION START: | 1-Sep-2013 | |||
| CONSTRUCTION COMPLETION: | 30-Aug-2014 | |||
| ESCROW AMENDMENT | No: | |||
| MONITORING PLAN APPROVAL: | ||||
| O and M PLAN APPROVAL: | ||||
| DEAUTHORIZATION DATE: | ||||
| CASH FLOW PROECTS: | ||||
| Phase 1 Approval: | 10/18/2006 | ( Actual ) | ||
| Phase 2 Approval: |
LEGISLATIVE DISTRICTS:
| CONGRESSIONAL DISTRICT: | 1 | Steve Scalise |
| STATE SENATE DISTRICT: | 999 | Not Available |
| STATE HOUSE DISTRICT: | 999 | Not Available |
Point of Contact:
DEPT. OF AGRICULTURE
NATURAL RESOURCES CONSERVATION SERVICE
| John Jurgensen 3737 Government Street Water Resources Office Alexandria, LA 71302 |
|
PROJECT STATUS REPORT as of 18-Jun-2013
Alligator Bend Marsh Restoration and Shoreline Protection
PROJECT LOCATION:
PROJECT DESCRIPTION:
PROJECT STATUS: (Project Status Last Updated: 9-Mar-2012 )
Project Design was completed in November 2011. Task Force did not approve funding for construction at January 2012 meeting. Project will request funding again at the January 2013 meeting.
FUND STATUS:
The current project estimate is $1,660,985 , which includes $1,660,985 for construction first costs, and $0 and $0 for 20 years of monitoring and operations and maintenance, respectively.