Sample CWPPRA Projects Mitigating Sea-level Rise

Project Number Project Title Description of Project Work Net Acres at 20 years Completion Date Construction Status
AT-2 Atchafalaya Sediment Delivery Channel dredging to enhance natural sediment delivery 2,232 21-Mar-98 Construction complete; Monitoring in progress
AT-3 Big Island Sediment Distribution Channel dredging to enhance natural sediment delivery 1,560 8-Oct-98 Construction complete; Monitoring in progress
AT-4 Castille Pass Channel Sediment Delivery Channel dredging to enhance natural sediment delivery 589 Unscheduled Engineering and design phase
BA-3c Naomi Outfall Management Construction of weirs with boat bays to maximize sediment retention and nutrient uptake 633 7-Jul-02 Construction complete
BA-21-2 Pass Chaland to Grand Bayou Pass Barrier Shoreline Restoration Creation of marsh platform and six, one-acre ponds to be seeded aerially 161 1-Aug-04 Engineering and design phase
BA-24 Myrtle Grove Siphon Installation of eight siphon pipes and vacuum pipe; construction of leveed outfall channel to facilitate distribution of water and sediments 1,119 Unscheduled Engineering and design phase
BA-25 Bayou Lafourche MR Reintroduction Installation of pump/siphon system, a receiving intake structure, discharge settling pond/sediment basin, weir structures and bank stabilization 988 Unscheduled Engineering and design phase
BA-28 Vegetative Plantings on Grand Terre Island Vegetative plantings; degradation of retention dikes to enhance fisheries; construction of fencing to reduce grazing 127 1-Jul-01 Construction complete; Monitoring in progress
BA-30 East/West Grand Terre Island Restoration Construction of 40 acres of dune, which will be planted with vegetation 472 1-Aug-04 Engineering and design phase
BA-33 Delta-building Diversion at Myrtle Grove Installation of five gated box culverts and a conveyance channel; construction of a pump station 8,891 Unscheduled Engineering and design phase
BA-34 Small Freshwater Diversion to Northwestern Barataria Installation of two small siphons, gap spoil banks and culverts * Unscheduled Engineering and design phase
BS-3a Caernarvon Diversion Outfall Management Construction of six armored plugs and maintenance of one plug; install culverts in seven existing plugs; restoration of spoilbanks to enhance freshwater flow and retention 802 19-Jun-02 Construction complete
BS-10 Delta-building Diversion North of Ft. St. Philip Installation of a new diversion channel and cuts made into the channel will divert water and sediments into adjacent open waters 2,473 1-Apr-04 Engineering and design phase
MR-3 West Bay Sediment Diversion Construction of a conveyance channel for diversion of sediments from the Mississippi River 9,831 30-Oct-04 Engineering and design phase
MR-6 Channel Armor Gap Crevasse Crevasse widening to enhance flow of fresh water and sediment 936 2-Nov-97 Construction complete; Monitoring in progress
MR-9 Delta Wide Crevasses Crevasse widening to enhance flow of fresh water and sediment 2,386 31-Dec-14 Construction phase
MR-13 Benny's Bay Diversion Installation of a conveyance channel for an uncontrolled sediment diversion 5,828 Unscheduled Engineering and design phase
PO-27 Chandeleur Island Marsh Restoration Vegetative plantings 220 1-Sep-03 Construction phase
PO-29 Diversion into Maurepas Swamp Construction of two box culverts, a receiving pond reinforced with riprap and a deep outflow channel to run from the Mississippi River to U.S. Interstate 10 N/A 30-Nov-08 Engineering and design phase
TE-20 Isle Dernieres Restoration, Phase 0 Use of existing sand for dune build-up; closure of breaches and construction of side dikes; suction dredging to fill areas within structures; vegetative plantings 9 15-Jun-99 Construction complete; Monitoring in progress
TE-24 Isle Dernieres Restoration, Phase 1 Dune build-up, breach closures, construction of side dikes; suction dredging; elevated-marsh platform creation; vegetative plantings 109 15-Jun-99 Construction complete; Monitoring in progress
TE-25 East Timbalier Island Restoration, Phase 1 Placement of dredged sand to create wetland habitats; addition of rock to existing breakwater to reduce wave-induced erosion 1,913 1-May-01 Construction complete; Monitoring in progress
TE-27 Whiskey Island Restoration Placement of dredged materials for wetland creation; closure of the breach at Coupe Nouvelle; vegetative plantings 1,239 15-Jun-00 Construction complete; Monitoring in progress
TE-30 East Timbalier Island Restoration, Phase 2 Pumping of dredged sand to create dune and intertidal wetland habitats 215 01-Sep-02 Construction complete; Monitoring in progress
TE-32a Lake Boudreaux Freshwater Introduction Dredging and installation of sluice gates and outfall management structures for freshwater introduction; flood protection measures 619 1-Jan-03 Engineering and design phase
TE-37 New Cut Dune/Marsh Restoration Closure of the breach between Trinity and East Islands through direct creation of dune and marsh habitat 102 Unscheduled Engineering and design phase
TE-39 South Lake DeCade Freshwater Introduction Installation of a water control structure in the southern bank of Lake DeCade; provision of shoreline protection; weir removal 201 1-Sep-04 Engineering and design phase
TE-40 Timbalier Island Dune/Marsh Restoration Creation of dune and marsh to restore the eastern end of Timbalier Island 273 Unscheduled Engineering and design phase
TE-47 Ship Shoal: Whiskey West Flank Restoration Pumping of dredged sand to create dune and intertidal wetland habitats; vegetative plantings 182 Unscheduled Engineering and design phase
TE-48 Raccoon Island Shoreline Protection/Marsh Creation Construction of breakwaters; placement of dredged sand to create wetland habitats; vegetative plantings 167 Unscheduled Engineering and design phase

*No net acres are calculated for swamp projects. This project would benefit 5,134 acres.