PROJECT STATUS REPORT as of 03-Dec-2024
PROJECT DATA
PROJECT: Grand Bayou Ridge and Marsh Restoration |
PRIORITY LIST: 28 | PROJECT NO: | CWPPRA NO: BA-217 | DNR NO: BA-217 |
PROJECT TYPE: Marsh Restoration | NET ACRES BENEFITTED: 225 |
REGION: 2 | BASIN: Barataria | PARISH: Plaquemines |
LEAD AGENCY: FWS |
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA |
MILESTONES:
CSA EXECUTION: | ||||
DESIGN COMPLETION: | ||||
CONSTRUCTION START: | 4/23/2023 12:00:00 AM | * | ||
CONSTRUCTION COMPLETION: | 12/31/2025 12:00:00 AM | |||
ESCROW AMENDMENT | No: | |||
MONITORING PLAN APPROVAL: | ||||
O and M PLAN APPROVAL: | ||||
DEAUTHORIZATION DATE: | ||||
CASH FLOW PROECTS: | ||||
Phase 1 Approval: | 12-Feb-2019 | ( Actual ) | ||
Phase 2 Approval: | 01-Jan-2022 | * |
LEGISLATIVE DISTRICTS:
CONGRESSIONAL DISTRICT: | ||
STATE SENATE DISTRICT: | ||
STATE HOUSE DISTRICT: |
Point of Contact:
DEPT. OF THE INTERIOR
FISH & WILDLIFE SERVICE
Ronny Paille Senior Field Biologist 200 Dulles Dr. Lafayette, LA 70506 |
|
PROJECT STATUS REPORT as of 03-Dec-2024
Grand Bayou Ridge and Marsh Restoration
PROJECT LOCATION:
Barataria Basin, Plaquemines Parish, Southeast of Lake Hermitage along the western bank of Grand Bayou
PROJECT DESCRIPTION:
The project includes 249 acres of marsh creation/nourishment and 8,740 linear fee (9 acres) of ridge restoration.
PROJECT STATUS: (Project Status Last Updated: 20-Aug-2024 )
The project was approved for Phase 2 in January 2023. A construction contract was awarded to Weeks Marine in June 2024. Construction is scheduled to begin in September 2024.
FUND STATUS:
The current project estimate is $51,174,431 , which includes $50,381,006 for construction first costs, and $303,891 and $489,534 for 20 years of monitoring and operations and maintenance, respectively.
LaCoast.gov | Project Managers' Technical Factsheet |