PROJECT STATUS REPORT as of 21-Nov-2024
PROJECT DATA
PROJECT: Northeast Turtle Bay Marsh Creation |
PRIORITY LIST: 31 | PROJECT NO: | CWPPRA NO: BA-258 | DNR NO: BA-258 |
PROJECT TYPE: | NET ACRES BENEFITTED: 343 |
REGION: 2 | BASIN: Barataria | PARISH: Jefferson |
LEAD AGENCY: NRCS |
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA |
MILESTONES:
CSA EXECUTION: | ||||
DESIGN COMPLETION: | ||||
CONSTRUCTION START: | ||||
CONSTRUCTION COMPLETION: | ||||
ESCROW AMENDMENT | No: | |||
MONITORING PLAN APPROVAL: | ||||
O and M PLAN APPROVAL: | ||||
DEAUTHORIZATION DATE: | ||||
CASH FLOW PROECTS: | ||||
Phase 1 Approval: | 27-Jan-2022 | ( Actual ) | ||
Phase 2 Approval: |
LEGISLATIVE DISTRICTS:
CONGRESSIONAL DISTRICT: | ||
STATE SENATE DISTRICT: | ||
STATE HOUSE DISTRICT: |
Point of Contact:
DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE
Quin Kinler Denham Springs, LA |
|
PROJECT STATUS REPORT as of 21-Nov-2024
Northeast Turtle Bay Marsh Creation
PROJECT LOCATION:
PROJECT DESCRIPTION:
PROJECT STATUS: (Project Status Last Updated: )
FUND STATUS:
The current project estimate is $3,591,775 , which includes $3,591,775 for construction first costs, and $0 and $0 for 20 years of monitoring and operations and maintenance, respectively.
LaCoast.gov | Project Managers' Technical Factsheet |