COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 21-Nov-2024

Barataria Basin Landbridge Shoreline Protection, Ph 3

PROJECT DATA

PROJECT: Barataria Basin Landbridge Shoreline Protection, Ph 3
PRIORITY LIST: 9 PROJECT NO: 0915 CWPPRA NO: XBA-63iii DNR NO: BA-27c
PROJECT TYPE: Shoreline Protection NET ACRES BENEFITTED: 264
REGION: 2 BASIN: Barataria PARISH: Jefferson
LEAD AGENCY: NRCS
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA

MILESTONES:

CSA EXECUTION: 25-Jul-2000 ( Actual )    
DESIGN COMPLETION: 15-Oct-2002 ( Actual )    
CONSTRUCTION START: 20-Oct-2003 ( Actual )    
CONSTRUCTION COMPLETION: 30-Sep-2017 ( Actual )    
ESCROW AMENDMENT 21-May-2002 ( Actual ) No: 97
MONITORING PLAN APPROVAL:    
O and M PLAN APPROVAL: 24-Feb-2005 ( Actual )    
DEAUTHORIZATION DATE:      
CASH FLOW PROECTS:        
Phase 1 Approval: 11-Jan-2000 ( Actual )    
Phase 2 Approval: 16-Jan-2002 ( Actual )    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT: 1 Steve Scalise
STATE SENATE DISTRICT: 20 Norby Chabert
STATE HOUSE DISTRICT: 54 Jerry Gisclair

Point of Contact:

DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE

Quin Kinler



Denham Springs, LA 
PHONES:  
Office:
Fax:

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 21-Nov-2024

Barataria Basin Landbridge Shoreline Protection, Ph 3

PROJECT LOCATION:

This project is located along the west bank of Bayou Perot and the north shoreline of Little Lake in Lafourche Parish and along the east bank of Bayous Rigolettes and Perot in Jefferson Parish.

PROJECT DESCRIPTION:

The project encompasses about 42,370 feet of shoreline protection.

PROJECT STATUS: (Project Status Last Updated: 22-Sep-2017 )

Construction Units 7&8 were completed in February 2017, with exception of about 400 feet with poor underlying soils. An additional construction contract will be issued to address this 400-foot section.

FUND STATUS:

The current project estimate is $37,964,129 , which includes $37,073,230 for construction first costs, and $133,520 and $757,379 for 20 years of monitoring and operations and maintenance, respectively.

LaCoast.gov Project Managers' Technical Factsheet