PROJECT STATUS REPORT as of 22-Nov-2024
PROJECT DATA
PROJECT: Barataria Basin Landbridge Shoreline Protection, Ph 4 |
PRIORITY LIST: 11 | PROJECT NO: 1112 | CWPPRA NO: BA-24-4 | DNR NO: BA-27d |
PROJECT TYPE: Shoreline Protection | NET ACRES BENEFITTED: 256 |
REGION: 2 | BASIN: Barataria | PARISH: Jefferson |
LEAD AGENCY: NRCS |
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA |
MILESTONES:
CSA EXECUTION: | 09-May-2002 | ( Actual ) | ||
DESIGN COMPLETION: | ||||
CONSTRUCTION START: | 27-Apr-2005 | ( Actual ) | ||
CONSTRUCTION COMPLETION: | 26-Apr-2006 | ( Actual ) | ||
ESCROW AMENDMENT | 27-Oct-2003 | ( Actual ) | No: | 106 |
MONITORING PLAN APPROVAL: | ||||
O and M PLAN APPROVAL: | ||||
DEAUTHORIZATION DATE: | ||||
CASH FLOW PROECTS: | ||||
Phase 1 Approval: | 16-Jan-2002 | ( Actual ) | ||
Phase 2 Approval: | 28-Jan-2004 | ( Actual ) |
LEGISLATIVE DISTRICTS:
CONGRESSIONAL DISTRICT: | 1 | Steve Scalise |
STATE SENATE DISTRICT: | 8 | John A. Alario, Jr. |
STATE HOUSE DISTRICT: | 105 | Christopher J. Leopold |
Point of Contact:
DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE
Quin Kinler Denham Springs, LA |
|
PROJECT STATUS REPORT as of 22-Nov-2024
Barataria Basin Landbridge Shoreline Protection, Ph 4
PROJECT LOCATION:
This project is located in Jefferson Parish along the east bank of Bayou Rigolettes.
PROJECT DESCRIPTION:
This project consists of 30,500 feet of foreshore rock dike and incorporates "fish dips" and openings at historic natural channels to eliminate shoreline erosion and deterioration of the Barataria landbridge.
PROJECT STATUS: (Project Status Last Updated: 12-Oct-2006 )
Construction Unit #6 was completed on April 26, 2006.
FUND STATUS:
The current project estimate is $13,195,423 , which includes $6,527,303 for construction first costs, and $20,645 and $6,647,475 for 20 years of monitoring and operations and maintenance, respectively.