PROJECT STATUS REPORT as of 26-Dec-2024
PROJECT DATA
PROJECT: LA Highway 1 Marsh Creation DEAUTHORIZED |
PRIORITY LIST: 9 | PROJECT NO: 0905 | CWPPRA NO: BA-32a | DNR NO: BA-29 |
PROJECT TYPE: Marsh Creation | NET ACRES BENEFITTED: |
REGION: 2 | BASIN: Barataria | PARISH: Lafourche |
LEAD AGENCY: EPA |
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA |
MILESTONES:
CSA EXECUTION: | 05-Oct-2000 | ( Actual ) | ||
DESIGN COMPLETION: | ||||
CONSTRUCTION START: | ||||
CONSTRUCTION COMPLETION: | ||||
ESCROW AMENDMENT | 02-Mar-2001 | ( Actual ) | No: | 82 |
MONITORING PLAN APPROVAL: | ||||
O and M PLAN APPROVAL: | ||||
DEAUTHORIZATION DATE: | 17-Feb-2005 | |||
CASH FLOW PROECTS: | ||||
Phase 1 Approval: | 11-Jan-2000 | ( Actual ) | ||
Phase 2 Approval: |
LEGISLATIVE DISTRICTS:
CONGRESSIONAL DISTRICT: | 1 | Steve Scalise |
STATE SENATE DISTRICT: | 999 | Not Available |
STATE HOUSE DISTRICT: | 999 | Not Available |
Point of Contact:
ENVIRONMENTAL PROTECTION AGENCY
REGION 6
Karen McCormick EPA R6 (WQ-EC) 1445 Ross Avenue Dallas, TX 75202-2733 |
|
PROJECT STATUS REPORT as of 26-Dec-2024
LA Highway 1 Marsh Creation DEAUTHORIZED
PROJECT LOCATION:
The project is located adjacent to Highway LA 1 and south of the Leeville Bridge.
PROJECT DESCRIPTION:
Approximately 150 acres of marsh platform will be created with a sediment dredged from nearby water bottoms.
PROJECT STATUS: (Project Status Last Updated: 14-Mar-2005 )
The project was deauthorized at the February 17, 2005 Task Force meeting.
FUND STATUS:
The current project estimate is $250,257 , which includes $245,644 for construction first costs, and $4,614 and $0 for 20 years of monitoring and operations and maintenance, respectively.