COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 19-Apr-2024

Little Lake Shoreline Protection/Dedicated Dredging near Round Lake

PROJECT DATA

PROJECT: Little Lake Shoreline Protection/Dedicated Dredging near Round Lake
PRIORITY LIST: 11 PROJECT NO: 1110 CWPPRA NO: BA-37 DNR NO: BA-37
PROJECT TYPE: Shoreline Protection NET ACRES BENEFITTED: 713
REGION: 2 BASIN: Barataria PARISH: Lafourche
LEAD AGENCY: NMFS
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA

MILESTONES:

CSA EXECUTION: 06-Aug-2002 ( Actual )    
DESIGN COMPLETION: 11-Sep-2003 ( Actual )    
CONSTRUCTION START: 04-Aug-2005 ( Actual )    
CONSTRUCTION COMPLETION: 30-Mar-2007 ( Actual )    
ESCROW AMENDMENT No:
MONITORING PLAN APPROVAL: 09-Jan-2006 ( Actual )    
O and M PLAN APPROVAL: 27-Oct-2008 ( Actual )    
DEAUTHORIZATION DATE:      
CASH FLOW PROECTS:        
Phase 1 Approval: 16-Jan-2002 ( Actual )    
Phase 2 Approval: 12-Nov-2003 ( Actual )    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT: 1 Steve Scalise
STATE SENATE DISTRICT: 20 Norby Chabert
STATE HOUSE DISTRICT: 54 Jerry Gisclair

Point of Contact:

DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE

Donna Rogers



,  
PHONES:  
Office:
Fax:

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 19-Apr-2024

Little Lake Shoreline Protection/Dedicated Dredging near Round Lake

PROJECT LOCATION:

The project is located in the central Barataria Basin in Lafourche Parish, Louisiana. The project area is generally bound by the East and West Forks of Bayou L'Ours and the southern shoreline of Little Lake from Plum Point westward to Breton Canal.

PROJECT DESCRIPTION:

The project would entail construction of approximately 21,000 feet along the Little Lake Shoreline from John the Fool Bayou to Breton Canal. The project would also include dedicated dredging from Little Lake to create approximately 488 acres of marsh at intertidal elevation and nourish 532 acres of fragmented, subsiding marsh.

PROJECT STATUS: (Project Status Last Updated: 29-Aug-2011 )

The 2011 Annual O&M inspection revealed that the rock dike along the northern section of the project (Sections 1-9 of 26 total sections) hd settled. A survey will be initiated on September 7 to help determine the extent of settlement. Project team should have the survey report by mid-October to consider a maintenance event.

FUND STATUS:

The current project estimate is $23,326,119 , which includes $21,703,176 for construction first costs, and $98,136 and $1,524,807 for 20 years of monitoring and operations and maintenance, respectively.

LaCoast.gov Project Managers' Technical Factsheet