PROJECT STATUS REPORT as of 26-Dec-2024
PROJECT DATA
PROJECT: Caernarvon Diversion Outfall Management |
PRIORITY LIST: 2 | PROJECT NO: 0219 | CWPPRA NO: BS-3a | DNR NO: BS-03a |
PROJECT TYPE: Outfall Management | NET ACRES BENEFITTED: 802 |
REGION: 2 | BASIN: Breton Sound | PARISH: Plaquemines |
LEAD AGENCY: NRCS |
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA. |
MILESTONES:
CSA EXECUTION: | 13-Oct-1994 | ( Actual ) | ||
DESIGN COMPLETION: | 01-Jun-2000 | ( Actual ) | ||
CONSTRUCTION START: | 01-Jun-2001 | ( Actual ) | ||
CONSTRUCTION COMPLETION: | 19-Jun-2002 | ( Actual ) | ||
ESCROW AMENDMENT | 15-Sep-1995 | ( Actual ) | No: | 27 |
MONITORING PLAN APPROVAL: | ||||
O and M PLAN APPROVAL: | 01-May-2003 | ( Actual ) | ||
DEAUTHORIZATION DATE: | ||||
CASH FLOW PROECTS: | ||||
Phase 1 Approval: | 19-Oct-1992 | ( Actual ) | ||
Phase 2 Approval: | 19-Oct-1992 | ( Actual ) |
LEGISLATIVE DISTRICTS:
CONGRESSIONAL DISTRICT: | 1 | Steve Scalise |
STATE SENATE DISTRICT: | 1 | A. G. Crowe |
STATE HOUSE DISTRICT: | 105 | Christopher J. Leopold |
Point of Contact:
DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE
Quin Kinler Denham Springs, LA |
|
PROJECT STATUS REPORT as of 26-Dec-2024
Caernarvon Diversion Outfall Management
PROJECT LOCATION:
PROJECT DESCRIPTION:
The primary objective is to enhance marsh by increasing the utilization of freshwater, nutrients, and sediments provided by the Mississippi River through the Caernarvon Freshwater Diversion Structure. The proposed plan is still in the conceptual stages and focuses on the management of the diverted water. Outfall management in Plaquemines Parish would include lengthening the containment levee, constructing earthen dams, and removing elevated spoil banks to direct diversion discharge away from major channels and into the marsh and shallow pond area to the south of Big Mar.
PROJECT STATUS: (Project Status Last Updated: 03-Jul-2002 )
This project was proposed for deauthorization in December 1996, but was referred for revisions at the request of the landowners and DNR. The project was modified. The final plan/EA has been prepared. Bids were opened 23 February 2001. The low bid exceeded the funds available. Task Force approved additional funds. Construction complete June 19, 2002.
FUND STATUS:
The current project estimate is $4,536,000 , which includes $2,526,130 for construction first costs, and $837,103 and $1,172,767 for 20 years of monitoring and operations and maintenance, respectively.