PROJECT STATUS REPORT as of 21-Nov-2024
PROJECT DATA
PROJECT: Delta Management at Fort St. Philip |
PRIORITY LIST: 10 | PROJECT NO: 1006 | CWPPRA NO: BS-11 | DNR NO: BS-11 |
PROJECT TYPE: Sediment Diversion | NET ACRES BENEFITTED: 267 |
REGION: 2 | BASIN: Breton Sound | PARISH: Plaquemines |
LEAD AGENCY: FWS |
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA |
MILESTONES:
CSA EXECUTION: | 16-May-2001 | ( Actual ) | ||
DESIGN COMPLETION: | 17-May-2002 | ( Actual ) | ||
CONSTRUCTION START: | 19-Jun-2006 | ( Actual ) | ||
CONSTRUCTION COMPLETION: | 14-Dec-2006 | ( Actual ) | ||
ESCROW AMENDMENT | 21-May-2002 | ( Actual ) | No: | 90 |
MONITORING PLAN APPROVAL: | 20-Aug-2003 | ( Actual ) | ||
O and M PLAN APPROVAL: | 13-May-2007 | ( Actual ) | ||
DEAUTHORIZATION DATE: | ||||
CASH FLOW PROECTS: | ||||
Phase 1 Approval: | 10-Jan-2001 | ( Actual ) | ||
Phase 2 Approval: | 07-Aug-2002 | ( Actual ) |
LEGISLATIVE DISTRICTS:
CONGRESSIONAL DISTRICT: | 1 | Steve Scalise |
STATE SENATE DISTRICT: | 1 | A. G. Crowe |
STATE HOUSE DISTRICT: | 105 | Christopher J. Leopold |
Point of Contact:
DEPT. OF THE INTERIOR
FISH & WILDLIFE SERVICE
Kevin Roy Fish and Wildlife Biologist 200 Dulles Dr. Lafayette, LA 70506 |
|
PROJECT STATUS REPORT as of 21-Nov-2024
Delta Management at Fort St. Philip
PROJECT LOCATION:
The project is located in Plaquemines Parish on the east bank of the Mississippi River across from Fort Jackson.
PROJECT DESCRIPTION:
The objective of the project is to enhance the delta-building process occurring as a result of the crevasse at Fort St. Philip. Six artificial crevasses will be constructed to divert fresh water and sediments into areas currently restricted by spoil banks or natural ridges. The crevasses will be maintained during the project life. In addition, linear terraces will be constructed to enhance sediment retention and reduce wave energy in one of the large receiving bays. Vegetative plantings will be installed on the terraces.
PROJECT STATUS: (Project Status Last Updated: 19-Feb-2021 )
The project was completed in 2006. No maintenance has been conducted and monitoring activities are ongoing. The project will expire in 2026.
FUND STATUS:
The current project estimate is $2,544,882 , which includes $1,542,062 for construction first costs, and $498,361 and $504,459 for 20 years of monitoring and operations and maintenance, respectively.