PROJECT STATUS REPORT as of 22-Nov-2024
PROJECT DATA
PROJECT: Bertrandville Siphon DEAUTHORIZED |
PRIORITY LIST: 18 | PROJECT NO: 1804 | CWPPRA NO: BS-18 | DNR NO: BS-18 |
PROJECT TYPE: Freshwater Diversion | NET ACRES BENEFITTED: |
REGION: 2 | BASIN: Breton Sound | PARISH: Plaquemines |
LEAD AGENCY: EPA |
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA |
MILESTONES:
CSA EXECUTION: | 15-Jun-2011 | ( Actual ) | ||
DESIGN COMPLETION: | 4/8/2014 12:00:00 AM | * | ||
CONSTRUCTION START: | ||||
CONSTRUCTION COMPLETION: | ||||
ESCROW AMENDMENT | No: | |||
MONITORING PLAN APPROVAL: | ||||
O and M PLAN APPROVAL: | ||||
DEAUTHORIZATION DATE: | 16-Jan-2014 | |||
CASH FLOW PROECTS: | ||||
Phase 1 Approval: | 21-Jan-2009 | ( Actual ) | ||
Phase 2 Approval: | 21-Jan-2015 | * |
LEGISLATIVE DISTRICTS:
CONGRESSIONAL DISTRICT: | 1 | Steve Scalise |
STATE SENATE DISTRICT: | 999 | Not Available |
STATE HOUSE DISTRICT: | 999 | Not Available |
Point of Contact:
ENVIRONMENTAL PROTECTION AGENCY
REGION 6
Paul Kaspar EPA Region 6 (6WQ-EC) 1445 Ross Ave Dallas, TX 75202 |
|
PROJECT STATUS REPORT as of 22-Nov-2024
Bertrandville Siphon DEAUTHORIZED
PROJECT LOCATION:
PROJECT DESCRIPTION:
PROJECT STATUS: (Project Status Last Updated: 21-Jan-2013 )
Project delays due to considerations of State Master Plan consistency and pursuit of landowner support.
FUND STATUS:
The current project estimate is $521,984 , which includes $521,607 for construction first costs, and $377 and $0 for 20 years of monitoring and operations and maintenance, respectively.
LaCoast.gov | Project Managers' Technical Factsheet |