PROJECT STATUS REPORT as of 04-Oct-2024
PROJECT DATA
PROJECT: Mid Breton Landbridge Marsh Creation and Terracing |
PRIORITY LIST: 27 | PROJECT NO: | CWPPRA NO: BS-32 | DNR NO: BS-32 |
PROJECT TYPE: Marsh Creation | NET ACRES BENEFITTED: 411 |
REGION: 2 | BASIN: Breton Sound | PARISH: Plaquemines |
LEAD AGENCY: FWS |
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA |
MILESTONES:
CSA EXECUTION: | 30-Jan-2019 | ( Actual ) | ||
DESIGN COMPLETION: | 9/1/2022 12:00:00 AM | * | ||
CONSTRUCTION START: | ||||
CONSTRUCTION COMPLETION: | 12/31/2023 12:00:00 AM | * | ||
ESCROW AMENDMENT | No: | |||
MONITORING PLAN APPROVAL: | ||||
O and M PLAN APPROVAL: | ||||
DEAUTHORIZATION DATE: | ||||
CASH FLOW PROECTS: | ||||
Phase 1 Approval: | 09-Feb-2018 | ( Actual ) | ||
Phase 2 Approval: | 22-Jan-2021 | ( Actual ) |
LEGISLATIVE DISTRICTS:
CONGRESSIONAL DISTRICT: | ||
STATE SENATE DISTRICT: | ||
STATE HOUSE DISTRICT: |
Point of Contact:
DEPT. OF THE INTERIOR
FISH & WILDLIFE SERVICE
Darryl Clark Senior Field Biologist 200 Dulles Dr. Lafayette, LA 70506 |
|
PROJECT STATUS REPORT as of 04-Oct-2024
Mid Breton Landbridge Marsh Creation and Terracing
PROJECT LOCATION:
PROJECT DESCRIPTION:
PROJECT STATUS: (Project Status Last Updated: 12-Mar-2021 )
Currently the project team is acquiring land right agreements and applying for a 404 Permit from the Corps.
FUND STATUS:
The current project estimate is $35,800,369 , which includes $33,683,003 for construction first costs, and $199,758 and $1,917,608 for 20 years of monitoring and operations and maintenance, respectively.
LaCoast.gov | Project Managers' Technical Factsheet |