COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 21-Nov-2024

Mid Breton Landbridge Marsh Creation and Terracing

PROJECT DATA

PROJECT: Mid Breton Landbridge Marsh Creation and Terracing
PRIORITY LIST: 27 PROJECT NO: CWPPRA NO: BS-32 DNR NO: BS-32
PROJECT TYPE: Marsh Creation NET ACRES BENEFITTED: 411
REGION: 2 BASIN: Breton Sound PARISH: Plaquemines
LEAD AGENCY: FWS
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA

MILESTONES:

CSA EXECUTION: 30-Jan-2019 ( Actual )    
DESIGN COMPLETION: 9/1/2022 12:00:00 AM *    
CONSTRUCTION START:    
CONSTRUCTION COMPLETION: 12/31/2023 12:00:00 AM *    
ESCROW AMENDMENT No:
MONITORING PLAN APPROVAL:    
O and M PLAN APPROVAL:    
DEAUTHORIZATION DATE:      
CASH FLOW PROECTS:        
Phase 1 Approval: 09-Feb-2018 ( Actual )    
Phase 2 Approval: 22-Jan-2021 ( Actual )    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT:
STATE SENATE DISTRICT:
STATE HOUSE DISTRICT:

Point of Contact:

DEPT. OF THE INTERIOR
FISH & WILDLIFE SERVICE

Darryl Clark
Senior Field Biologist
200 Dulles Dr.

Lafayette, LA 70506
PHONES:  
Office: (337) 291-3111
Fax: (337) 291-3139

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 21-Nov-2024

Mid Breton Landbridge Marsh Creation and Terracing

PROJECT LOCATION:

PROJECT DESCRIPTION:


PROJECT STATUS: (Project Status Last Updated: 12-Mar-2021 )

Currently the project team is acquiring land right agreements and applying for a 404 Permit from the Corps.

FUND STATUS:

The current project estimate is $35,800,369 , which includes $33,683,003 for construction first costs, and $199,758 and $1,917,608 for 20 years of monitoring and operations and maintenance, respectively.

LaCoast.gov Project Managers' Technical Factsheet