PROJECT STATUS REPORT as of 21-Nov-2025
PROJECT DATA
| PROJECT: Yscloskey Marsh Creation |
| PRIORITY LIST: 32 | PROJECT NO: | CWPPRA NO: | DNR NO: BS-46 |
| PROJECT TYPE: Marsh Creation | NET ACRES BENEFITTED: 306 |
| REGION: 2 | BASIN: Breton Sound | PARISH: St. Bernard |
| LEAD AGENCY: |
| LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA |
MILESTONES:
| CSA EXECUTION: | ||||
| DESIGN COMPLETION: | ||||
| CONSTRUCTION START: | ||||
| CONSTRUCTION COMPLETION: | ||||
| ESCROW AMENDMENT | No: | |||
| MONITORING PLAN APPROVAL: | ||||
| O and M PLAN APPROVAL: | ||||
| DEAUTHORIZATION DATE: | ||||
| CASH FLOW PROECTS: | ||||
| Phase 1 Approval: | 26-Jan-2023 | ( Actual ) | ||
| Phase 2 Approval: |
LEGISLATIVE DISTRICTS:
| CONGRESSIONAL DISTRICT: | ||
| STATE SENATE DISTRICT: | ||
| STATE HOUSE DISTRICT: |
Point of Contact:
DEPT. OF THE INTERIOR
FISH & WILDLIFE SERVICE
|
Darryl Clark Senior Field Biologist 200 Dulles Dr. Lafayette, LA 70506 |
|
PROJECT STATUS REPORT as of 21-Nov-2025
Yscloskey Marsh Creation
PROJECT LOCATION:
PROJECT DESCRIPTION:
PROJECT STATUS: (Project Status Last Updated: )
FUND STATUS:
The current project estimate is $3,741,913 , which includes $3,741,913 for construction first costs, and $0 and $0 for 20 years of monitoring and operations and maintenance, respectively.