COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 20-Dec-2024

Sweet Lake/Willow Lake Hydrologic Restoration

PROJECT DATA

PROJECT: Sweet Lake/Willow Lake Hydrologic Restoration
PRIORITY LIST: 5 PROJECT NO: 0562 CWPPRA NO: CS-11b DNR NO: CS-11b
PROJECT TYPE: Shoreline Protection NET ACRES BENEFITTED: 247
REGION: 4 BASIN: Calcasieu/Sabine PARISH: Cameron
LEAD AGENCY: NRCS
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA.

MILESTONES:

CSA EXECUTION: 23-Jun-1997 ( Actual )    
DESIGN COMPLETION: 31-Mar-1998 ( Actual )    
CONSTRUCTION START: 01-Nov-1999 ( Actual )    
CONSTRUCTION COMPLETION: 02-Oct-2002 ( Actual )    
ESCROW AMENDMENT 25-Aug-1997 ( Actual ) No: 54
MONITORING PLAN APPROVAL: 21-Oct-1998 ( Actual )    
O and M PLAN APPROVAL: 10-Apr-2003 ( Actual )    
DEAUTHORIZATION DATE:      
CASH FLOW PROECTS:        
Phase 1 Approval: 28-Feb-1996 ( Actual )    
Phase 2 Approval: 28-Feb-1996 ( Actual )    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT: 3 Charles W. Boustany
STATE SENATE DISTRICT: 27 Ronnie Johns
STATE HOUSE DISTRICT: 33 Michael E. Danahay

Point of Contact:

DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE

Quin Kinler



Denham Springs, LA 
PHONES:  
Office:
Fax:

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 20-Dec-2024

Sweet Lake/Willow Lake Hydrologic Restoration

PROJECT LOCATION:

PROJECT DESCRIPTION:

The northern shoreline of the GIWW has eroded into Sweet Lake for approximately 1.3 miles and into Willow Lake for approximately 0.5 miles, increasing turbidity in the waters of these lakes. The project objectives are to reestablish the shoreline (hydrologic boundary) between Sweet Lake and the GIWW, to reduce lake turbidity and tidal exchange, and to halt erosin and trap sediments needed to rebuild marsh along the northern and northwestern shorelines of Sweet Lake.

PROJECT STATUS: (Project Status Last Updated: 06-Dec-2002 )

The rock bank protection feature of the project is complete. The second contract has been awarded; terrace construction and vegetative planting will be finished by October 1, 2002. Contractor was unable to complete the construction. Contract terminated; remaining work was advertised December 2001. Contract awarded, and construction completed October 2, 2002.

FUND STATUS:

The current project estimate is $3,929,152 , which includes $3,289,390 for construction first costs, and $161,249 and $478,513 for 20 years of monitoring and operations and maintenance, respectively.

LaCoast.gov Project Managers' Technical Factsheet