COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 21-Nov-2024

Perry Ridge Shore Protection

PROJECT DATA

PROJECT: Perry Ridge Shore Protection
PRIORITY LIST: 4 PROJECT NO: 0451 CWPPRA NO: PCS-26 DNR NO: CS-24
PROJECT TYPE: Shoreline Protection NET ACRES BENEFITTED: 1203
REGION: 4 BASIN: Calcasieu/Sabine PARISH: Calcasieu
LEAD AGENCY: NRCS
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA

MILESTONES:

CSA EXECUTION: 23-Jun-1997 ( Actual )    
DESIGN COMPLETION: 30-Aug-1997 ( Actual )    
CONSTRUCTION START: 15-Dec-1998 ( Actual )    
CONSTRUCTION COMPLETION: 15-Feb-1999 ( Actual )    
ESCROW AMENDMENT 25-Aug-1997 ( Actual ) No: 53
MONITORING PLAN APPROVAL: 23-Jul-1997 ( Actual )    
O and M PLAN APPROVAL: 06-Dec-2000 ( Actual )    
DEAUTHORIZATION DATE:      
CASH FLOW PROECTS:        
Phase 1 Approval: 16-Dec-1994 ( Actual )    
Phase 2 Approval:    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT: 7 Not Available
STATE SENATE DISTRICT: 30 John R. Smith
STATE HOUSE DISTRICT: 33 Michael E. Danahay

Point of Contact:

DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE

Quin Kinler



Denham Springs, LA 
PHONES:  
Office:
Fax:

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 21-Nov-2024

Perry Ridge Shore Protection

PROJECT LOCATION:

PROJECT DESCRIPTION:

The project will reduce tidal scour, wave action from boats, and other excessive energy impacts on interior marshes and the possibility of saltwater intrusion by repairing the northern spoil bank of the GIWW. Rip-rap will be placed along low areas of the northern bank of the GIWW from Perry Ridge to Vinton Drainage Canal. This will allow overbank flow over the rip-rap and deposition of sediments between rip-rap and marsh. Two inlets will be armored.

PROJECT STATUS: (Project Status Last Updated: 01-Jan-1990 )

Project complete.

FUND STATUS:

The current project estimate is $2,289,090 , which includes $1,710,877 for construction first costs, and $153,704 and $424,509 for 20 years of monitoring and operations and maintenance, respectively.