PROJECT STATUS REPORT as of 17-Jun-2026
PROJECT DATA
| PROJECT: Black Bayou Culverts Hydrologic Restoration |
| PRIORITY LIST: 9 | PROJECT NO: 0916 | CWPPRA NO: 28-5229 | DNR NO: CS-29 |
| PROJECT TYPE: Hydrologic Restoration | NET ACRES BENEFITTED: 540 |
| REGION: 4 | BASIN: Calcasieu/Sabine | PARISH: Cameron |
| LEAD AGENCY: NRCS |
| LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA |
MILESTONES:
| CSA EXECUTION: | 25-Jul-2000 | ( Actual ) | ||
| DESIGN COMPLETION: | 15-May-2004 | ( Actual ) | ||
| CONSTRUCTION START: | 25-May-2005 | ( Actual ) | ||
| CONSTRUCTION COMPLETION: | 26-Jan-2010 | ( Actual ) | ||
| ESCROW AMENDMENT | 21-May-2002 | ( Actual ) | No: | 99 |
| MONITORING PLAN APPROVAL: | ||||
| O and M PLAN APPROVAL: | ||||
| DEAUTHORIZATION DATE: | ||||
| CASH FLOW PROECTS: | ||||
| Phase 1 Approval: | 11-Jan-2000 | ( Actual ) | ||
| Phase 2 Approval: | 14-Aug-2003 | ( Actual ) |
LEGISLATIVE DISTRICTS:
| CONGRESSIONAL DISTRICT: | 3 | Charles W. Boustany |
| STATE SENATE DISTRICT: | 27 | Ronnie Johns |
| STATE HOUSE DISTRICT: | 33 | Michael E. Danahay |
Point of Contact:
DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE
|
Quin Kinler Denham Springs, LA |
|
PROJECT STATUS REPORT as of 17-Jun-2026
Black Bayou Culverts Hydrologic Restoration
PROJECT LOCATION:
This project is located east of Calcasieu Lake in Cameron Parish.
PROJECT DESCRIPTION:
Project consists of the installation of ten 10 foot by 10 foot concrete box culverts in Black Bayou at the intersection of Louisiana Highway 384 to allow discharge of excess water from the lakes subbasin.
PROJECT STATUS: (Project Status Last Updated: )
FUND STATUS:
The current project estimate is $16,789,107 , which includes $5,043,028 for construction first costs, and $725,143 and $11,020,936 for 20 years of monitoring and operations and maintenance, respectively.