COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 02-Dec-2024

Holly Beach Sand Management

PROJECT DATA

PROJECT: Holly Beach Sand Management
PRIORITY LIST: 11.1 PROJECT NO: 1102 CWPPRA NO: CS-31 DNR NO: CS-31
PROJECT TYPE: Shoreline Protection NET ACRES BENEFITTED: 330
REGION: 4 BASIN: Calcasieu/Sabine PARISH: Calcasieu
LEAD AGENCY: NRCS
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA

MILESTONES:

CSA EXECUTION: 09-May-2002 ( Actual )    
DESIGN COMPLETION: 01-Apr-2002 ( Actual )    
CONSTRUCTION START: 01-Aug-2002 ( Actual )    
CONSTRUCTION COMPLETION: 31-Mar-2003 ( Actual )    
ESCROW AMENDMENT 11-Jul-2002 ( Actual ) No: 103
MONITORING PLAN APPROVAL:    
O and M PLAN APPROVAL: 04-May-2004 ( Actual )    
DEAUTHORIZATION DATE:      
CASH FLOW PROECTS:        
Phase 1 Approval: 07-Aug-2001 ( Actual )    
Phase 2 Approval: 07-Aug-2001 ( Actual )    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT: 3 Charles W. Boustany
STATE SENATE DISTRICT: 25 Dan "Blade" Morrish
STATE HOUSE DISTRICT: 36 Chuck Kleckley

Point of Contact:

DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE

Quin Kinler



Denham Springs, LA 
PHONES:  
Office:
Fax:

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 02-Dec-2024

Holly Beach Sand Management

PROJECT LOCATION:

PROJECT DESCRIPTION:


PROJECT STATUS: (Project Status Last Updated: 12-Mar-2003 )

The placement of the sand material on to the beach was completed on Saturday, March 1, 2003. Required work that is now in progress consist of demobilization of the pipeline segments, dressing the completed beach work,erection of the Sand Fencing and installation of the vegetation.

FUND STATUS:

The current project estimate is $14,134,952 , which includes $13,509,233 for construction first costs, and $285,348 and $340,371 for 20 years of monitoring and operations and maintenance, respectively.