PROJECT STATUS REPORT as of 12-Jun-2026
PROJECT DATA
| PROJECT: Holly Beach Sand Management |
| PRIORITY LIST: 11.1 | PROJECT NO: 1102 | CWPPRA NO: CS-31 | DNR NO: CS-31 |
| PROJECT TYPE: Shoreline Protection | NET ACRES BENEFITTED: 330 |
| REGION: 4 | BASIN: Calcasieu/Sabine | PARISH: Calcasieu |
| LEAD AGENCY: NRCS |
| LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA |
MILESTONES:
| CSA EXECUTION: | 09-May-2002 | ( Actual ) | ||
| DESIGN COMPLETION: | 01-Apr-2002 | ( Actual ) | ||
| CONSTRUCTION START: | 01-Aug-2002 | ( Actual ) | ||
| CONSTRUCTION COMPLETION: | 31-Mar-2003 | ( Actual ) | ||
| ESCROW AMENDMENT | 11-Jul-2002 | ( Actual ) | No: | 103 |
| MONITORING PLAN APPROVAL: | ||||
| O and M PLAN APPROVAL: | 04-May-2004 | ( Actual ) | ||
| DEAUTHORIZATION DATE: | ||||
| CASH FLOW PROECTS: | ||||
| Phase 1 Approval: | 07-Aug-2001 | ( Actual ) | ||
| Phase 2 Approval: | 07-Aug-2001 | ( Actual ) |
LEGISLATIVE DISTRICTS:
| CONGRESSIONAL DISTRICT: | 3 | Charles W. Boustany |
| STATE SENATE DISTRICT: | 25 | Dan "Blade" Morrish |
| STATE HOUSE DISTRICT: | 36 | Chuck Kleckley |
Point of Contact:
DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE
|
Quin Kinler Denham Springs, LA |
|
PROJECT STATUS REPORT as of 12-Jun-2026
Holly Beach Sand Management
PROJECT LOCATION:
PROJECT DESCRIPTION:
PROJECT STATUS: (Project Status Last Updated: )
FUND STATUS:
The current project estimate is $14,136,374 , which includes $13,509,233 for construction first costs, and $281,371 and $345,770 for 20 years of monitoring and operations and maintenance, respectively.
| LaCoast.gov | Project Managers' Technical Factsheet |