PROJECT STATUS REPORT as of 20-Dec-2024
PROJECT DATA
PROJECT: Cameron-Creole Freshwater Introduction |
PRIORITY LIST: 18 | PROJECT NO: 1801 | CWPPRA NO: CS-49 | DNR NO: CS-49 |
PROJECT TYPE: Freshwater Diversion | NET ACRES BENEFITTED: 218 |
REGION: 4 | BASIN: Calcasieu/Sabine | PARISH: Cameron |
LEAD AGENCY: NRCS |
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA |
MILESTONES:
CSA EXECUTION: | 04-May-2009 | ( Actual ) | ||
DESIGN COMPLETION: | 11/1/2014 12:00:00 AM | * | ||
CONSTRUCTION START: | 04-Apr-2012 | ( Actual ) | ||
CONSTRUCTION COMPLETION: | 02-Dec-2021 | ( Actual ) | ||
ESCROW AMENDMENT | No: | |||
MONITORING PLAN APPROVAL: | ||||
O and M PLAN APPROVAL: | ||||
DEAUTHORIZATION DATE: | ||||
CASH FLOW PROECTS: | ||||
Phase 1 Approval: | 21-Jan-2009 | ( Actual ) | ||
Phase 2 Approval: | 20-Jan-2010 | ( Actual ) |
LEGISLATIVE DISTRICTS:
CONGRESSIONAL DISTRICT: | 3 | Charles W. Boustany |
STATE SENATE DISTRICT: | 999 | Not Available |
STATE HOUSE DISTRICT: | 999 | Not Available |
Point of Contact:
DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE
Quin Kinler Denham Springs, LA |
|
PROJECT STATUS REPORT as of 20-Dec-2024
Cameron-Creole Freshwater Introduction
PROJECT LOCATION:
PROJECT DESCRIPTION:
PROJECT STATUS: (Project Status Last Updated: 28-Nov-2016 )
Milestones shown above are for the vegetative component of the project only. Federal Sponsor does not have access to change the information relative to the structural components. Scheduled Dates: Phase II approval January 2018; Contracting April 2018; Construction Start September 2018
FUND STATUS:
The current project estimate is $21,295,345 , which includes $20,347,030 for construction first costs, and $161,051 and $787,264 for 20 years of monitoring and operations and maintenance, respectively.
LaCoast.gov | Project Managers' Technical Factsheet |