PROJECT STATUS REPORT as of 21-Nov-2024
PROJECT DATA
PROJECT: Sabine Marsh Creation Cycles 6 & 7 |
PRIORITY LIST: 27 | PROJECT NO: | CWPPRA NO: CS-81 | DNR NO: CS-81 |
PROJECT TYPE: Marsh Creation | NET ACRES BENEFITTED: 900 |
REGION: 4 | BASIN: Calcasieu/Sabine | PARISH: Cameron |
LEAD AGENCY: FWS |
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA |
MILESTONES:
CSA EXECUTION: | ||||
DESIGN COMPLETION: | ||||
CONSTRUCTION START: | ||||
CONSTRUCTION COMPLETION: | 6/1/2026 12:00:00 AM | |||
ESCROW AMENDMENT | No: | |||
MONITORING PLAN APPROVAL: | ||||
O and M PLAN APPROVAL: | ||||
DEAUTHORIZATION DATE: | ||||
CASH FLOW PROECTS: | ||||
Phase 1 Approval: | 09-Feb-2018 | ( Actual ) | ||
Phase 2 Approval: |
LEGISLATIVE DISTRICTS:
CONGRESSIONAL DISTRICT: | ||
STATE SENATE DISTRICT: | ||
STATE HOUSE DISTRICT: |
Point of Contact:
DEPT. OF THE INTERIOR
FISH & WILDLIFE SERVICE
Darryl Clark Senior Field Biologist 200 Dulles Dr. Lafayette, LA 70506 |
|
PROJECT STATUS REPORT as of 21-Nov-2024
Sabine Marsh Creation Cycles 6 & 7
PROJECT LOCATION:
PROJECT DESCRIPTION:
PROJECT STATUS: (Project Status Last Updated: 12-Mar-2021 )
Currently CPRA is collecting survey and geotechnical data for engineering and design of this project.
FUND STATUS:
The current project estimate is $3,824,731 , which includes $3,824,731 for construction first costs, and $0 and $0 for 20 years of monitoring and operations and maintenance, respectively.