PROJECT STATUS REPORT as of 16-Dec-2025
PROJECT DATA
| PROJECT: Sediment Containment System for Marsh Creation Demo |
| PRIORITY LIST: 17 | PROJECT NO: 1706 | CWPPRA NO: LA-09 | DNR NO: LA-09 |
| PROJECT TYPE: Demo | NET ACRES BENEFITTED: 0 |
| REGION: 0 | BASIN: Coastal Basins | PARISH: Coastal Parishes |
| LEAD AGENCY: NRCS |
| LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA |
MILESTONES:
| CSA EXECUTION: | 28-Jan-2008 | ( Actual ) | ||
| DESIGN COMPLETION: | ||||
| CONSTRUCTION START: | 08-Jan-2013 | ( Actual ) | ||
| CONSTRUCTION COMPLETION: | 11-Sep-2013 | ( Actual ) | ||
| ESCROW AMENDMENT | 09-Jun-2008 | ( Actual ) | No: | 116 |
| MONITORING PLAN APPROVAL: | ||||
| O and M PLAN APPROVAL: | ||||
| DEAUTHORIZATION DATE: | ||||
| CASH FLOW PROECTS: | ||||
| Phase 1 Approval: | 25-Oct-2007 | ( Actual ) | ||
| Phase 2 Approval: | 25-Oct-2007 | ( Actual ) |
LEGISLATIVE DISTRICTS:
| CONGRESSIONAL DISTRICT: | 1 | Steve Scalise |
| STATE SENATE DISTRICT: | 0 | Multiple |
| STATE HOUSE DISTRICT: | 0 | Multiple |
Point of Contact:
DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE
|
Quin Kinler Denham Springs, LA |
|
PROJECT STATUS REPORT as of 16-Dec-2025
Sediment Containment System for Marsh Creation Demo
PROJECT LOCATION:
PROJECT DESCRIPTION:
PROJECT STATUS: (Project Status Last Updated: 09-Jan-2013 )
LA-9 Demo Project was included with the PO-75 Pilot Study. Project was awarded on January 7, 2013.
FUND STATUS:
The current project estimate is $970,726 , which includes $883,702 for construction first costs, and $35,753 and $51,271 for 20 years of monitoring and operations and maintenance, respectively.