COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 20-Dec-2024

Non-Rock Alternatives to Shoreline Protection Demo

PROJECT DATA

PROJECT: Non-Rock Alternatives to Shoreline Protection Demo
PRIORITY LIST: 18 PROJECT NO: 1805 CWPPRA NO: LA-16 DNR NO: LA-16
PROJECT TYPE: Demo NET ACRES BENEFITTED: 0
REGION: 0 BASIN: Coastal Basins PARISH: Coastal Parishes
LEAD AGENCY: NRCS
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA

MILESTONES:

CSA EXECUTION: 04-May-2009 ( Actual )    
DESIGN COMPLETION: 11/26/2012 12:00:00 AM *    
CONSTRUCTION START: 05-Mar-2015 ( Actual )    
CONSTRUCTION COMPLETION: 31-Dec-2017 ( Actual )    
ESCROW AMENDMENT 22-Aug-2012 ( Actual ) No:
MONITORING PLAN APPROVAL:    
O and M PLAN APPROVAL:    
DEAUTHORIZATION DATE:      
CASH FLOW PROECTS:        
Phase 1 Approval: 21-Jan-2009 ( Actual )    
Phase 2 Approval: 21-Jan-2009 ( Actual )    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT: 0 Multiple
STATE SENATE DISTRICT: 0 Multiple
STATE HOUSE DISTRICT: 0 Multiple

Point of Contact:

DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE

Quin Kinler



Denham Springs, LA 
PHONES:  
Office:
Fax:

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 20-Dec-2024

Non-Rock Alternatives to Shoreline Protection Demo

PROJECT LOCATION:

PROJECT DESCRIPTION:


PROJECT STATUS: (Project Status Last Updated: 17-Apr-2012 )

Projected Timelines Project was advertised on Nov. 15, 2011 Site Visits Nov. 16 & 17, 2011 Proposals Due on RFP Mar. 15, 2012) < Phase I > Review of Proposals May 14, 2012) Interview Process June 28, 2012) < Phase 2 > Notice of Selection (for Phase 2 design) (July 13, 2012) Draft Design Schedule from NRCS (Aug. 3, 2012) Phase 2 Contract Award (Aug. 13, 2012) Final Design Schedule from NRCS (Aug. 17, 2012) Begin Surveys and Prepare P&S for advertisement (Sep. 19, 2012) Final Product Selection and Develop Phase III Budget (Nov. 26, 2012) Submit Budget Increase Request to Technical Committee (TC) (Nov. 27, 2012) Request Task Force Approval and Budget January 17, 2013 < Phase 3 > Notice of Selection (for Phase III) (Jan. 25, 2013) Advertise NRCS Dredging Contract (Mar. 18, 2013) Finalize NRCS Plans & Specifications (May 25, 2013) Phase 3 Contract Award (May 27, 2013) NTP on NRCS Dredging Contract (May 31, 2013) Construction of Shoreline Protection Systems(Jan. 22, 2014) Construction Report (Feb. 21, 2014) Monitoring Period (Jan. 23, 2017) Completion Report and Project Closeout (Apr. 24, 2017)

FUND STATUS:

The current project estimate is $6,076,557 , which includes $5,223,938 for construction first costs, and $572,195 and $280,424 for 20 years of monitoring and operations and maintenance, respectively.

LaCoast.gov Project Managers' Technical Factsheet