PROJECT STATUS REPORT as of 21-Nov-2024
PROJECT DATA
PROJECT: Vegetative Plantings - Dewitt-Rollover Planting Demo DEAUTHORIZED |
PRIORITY LIST: 1 | PROJECT NO: 0107-2 | CWPPRA NO: ME-8 | DNR NO: ME-08 |
PROJECT TYPE: Vegetative Plantings | NET ACRES BENEFITTED: |
REGION: 4 | BASIN: Mermentau | PARISH: Vermilion |
LEAD AGENCY: NRCS |
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA. |
MILESTONES:
CSA EXECUTION: | 17-Apr-1993 | ( Actual ) | ||
DESIGN COMPLETION: | 15-Feb-1994 | ( Actual ) | ||
CONSTRUCTION START: | 11-Jul-1994 | ( Actual ) | ||
CONSTRUCTION COMPLETION: | ||||
ESCROW AMENDMENT | 14-Mar-1994 | ( Actual ) | No: | 5 |
MONITORING PLAN APPROVAL: | 21-Jun-1995 | ( Actual ) | ||
O and M PLAN APPROVAL: | ||||
DEAUTHORIZATION DATE: | 28-Feb-1996 | |||
CASH FLOW PROECTS: | ||||
Phase 1 Approval: | 31-Oct-1991 | ( Actual ) | ||
Phase 2 Approval: |
LEGISLATIVE DISTRICTS:
CONGRESSIONAL DISTRICT: | 3 | Charles W. Boustany |
STATE SENATE DISTRICT: | 25 | Dan "Blade" Morrish |
STATE HOUSE DISTRICT: | 47 | Bob Hensgens |
Point of Contact:
DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE
Quin Kinler Denham Springs, LA |
|
PROJECT STATUS REPORT as of 21-Nov-2024
Vegetative Plantings - Dewitt-Rollover Planting Demo DEAUTHORIZED
PROJECT LOCATION:
The project is on the Gulf of Mexico shoreline in Vermilion Parish.
PROJECT DESCRIPTION:
The project's purpose is to establish a vegetative buffer between the Gulf and coastal wetlands, reduce wave energy and trap sediment.
PROJECT STATUS: (Project Status Last Updated: 01-Jan-1990 )
Sub-project of the Vegetative Plantings project. Complete and deauthorized.
FUND STATUS:
The current project estimate is $92,147 , which includes $88,425 for construction first costs, and $3,722 and $0 for 20 years of monitoring and operations and maintenance, respectively.