PROJECT STATUS REPORT as of 26-Dec-2024
PROJECT DATA
PROJECT: Cameron Prairie National Wildlife Refuge Shoreline Protection COMPLETE |
PRIORITY LIST: 1 | PROJECT NO: 0111 | CWPPRA NO: 229 | DNR NO: ME-09 |
PROJECT TYPE: Shoreline Protection | NET ACRES BENEFITTED: 247 |
REGION: 4 | BASIN: Mermentau | PARISH: Cameron |
LEAD AGENCY: FWS |
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA. |
MILESTONES:
CSA EXECUTION: | 17-Apr-1993 | ( Actual ) | ||
DESIGN COMPLETION: | 30-Aug-1992 | ( Actual ) | ||
CONSTRUCTION START: | 19-May-1994 | ( Actual ) | ||
CONSTRUCTION COMPLETION: | 09-Aug-1994 | ( Actual ) | ||
ESCROW AMENDMENT | 19-Oct-1993 | ( Actual ) | No: | 1 |
MONITORING PLAN APPROVAL: | 21-Jun-1995 | ( Actual ) | ||
O and M PLAN APPROVAL: | ||||
DEAUTHORIZATION DATE: | ||||
CASH FLOW PROECTS: | ||||
Phase 1 Approval: | 31-Oct-1991 | ( Actual ) | ||
Phase 2 Approval: |
LEGISLATIVE DISTRICTS:
CONGRESSIONAL DISTRICT: | 3 | Charles W. Boustany |
STATE SENATE DISTRICT: | 25 | Dan "Blade" Morrish |
STATE HOUSE DISTRICT: | 36 | Chuck Kleckley |
Point of Contact:
DEPT. OF THE INTERIOR
FISH & WILDLIFE SERVICE
Darryl Clark Senior Field Biologist 200 Dulles Dr. Lafayette, LA 70506 |
|
PROJECT STATUS REPORT as of 26-Dec-2024
Cameron Prairie National Wildlife Refuge Shoreline Protection COMPLETE
PROJECT LOCATION:
The project is located on the northern bank of the Gulf Intracoastal Waterway, east of the Gibbstown Bridge, in the southern portion of Cameron Prairie National Wildlife Refuge in Cameron Parish, LA.
PROJECT DESCRIPTION:
The project will protect the emergent wetlands of the Cameron Prairie National Wildlife Refuge adjacent to the GIWW, enhance the emergent wetlands protected by constructing approximately 2.5 miles of rock dike parallel to the existing spoil bank, and terminate the encroachment of the GIWW into the refuge.
PROJECT STATUS: (Project Status Last Updated: 19-Feb-2021 )
This project expired in 2014 and has been closed out. The structure was reported to be in good condition at the time of closeout.
FUND STATUS:
The current project estimate is $1,061,657 , which includes $912,887 for construction first costs, and $98,905 and $49,865 for 20 years of monitoring and operations and maintenance, respectively.
LaCoast.gov | Project Managers' Technical Factsheet |