COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 19-Apr-2024

Little Pecan Bayou Hydrologic Restoration DEAUTHORIZED

PROJECT DATA

PROJECT: Little Pecan Bayou Hydrologic Restoration DEAUTHORIZED
PRIORITY LIST: 9 PROJECT NO: 0917 CWPPRA NO: XME-42a DNR NO: ME-17
PROJECT TYPE: Hydrologic Restoration NET ACRES BENEFITTED:
REGION: 4 BASIN: Mermentau PARISH: Cameron
LEAD AGENCY: NRCS
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA

MILESTONES:

CSA EXECUTION: 25-Jul-2000 ( Actual )    
DESIGN COMPLETION:    
CONSTRUCTION START:    
CONSTRUCTION COMPLETION:    
ESCROW AMENDMENT 21-May-2002 ( Actual ) No: 96
MONITORING PLAN APPROVAL:    
O and M PLAN APPROVAL:    
DEAUTHORIZATION DATE: 05-Jun-2012      
CASH FLOW PROECTS:        
Phase 1 Approval: 11-Jan-2000 ( Actual )    
Phase 2 Approval:    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT: 3 Charles W. Boustany
STATE SENATE DISTRICT: 25 Dan "Blade" Morrish
STATE HOUSE DISTRICT: 36 Chuck Kleckley

Point of Contact:

DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE

Quin Kinler



Denham Springs, LA 
PHONES:  
Office:
Fax:

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 19-Apr-2024

Little Pecan Bayou Hydrologic Restoration DEAUTHORIZED

PROJECT LOCATION:

This project is located east of the Mermentau River in Cameron Parish, LA.

PROJECT DESCRIPTION:

The project encompasses approximately 24,600 acres of fresh to brackish marsh habitat. The project components include water control structures, conveyence channels, and terraces.

PROJECT STATUS: (Project Status Last Updated: 11-Jul-2012 )

Project was deauthorized at Spring 2012 Task Force meeting for the following reasons: • The current ME-17 project features do not yield sufficient wetland benefits to warrant a Phase II request for construction and twenty years of maintenance. • Within the current project scope, the CPRA has concerns over public vandalism.

FUND STATUS:

The current project estimate is $1,303,713 , which includes $1,220,273 for construction first costs, and $83,440 and $0 for 20 years of monitoring and operations and maintenance, respectively.

LaCoast.gov Project Managers' Technical Factsheet