PROJECT STATUS REPORT as of 21-Nov-2024
PROJECT DATA
PROJECT: Rockefeller Refuge Gulf Shoreline Stabilization |
PRIORITY LIST: 10 | PROJECT NO: 1010 | CWPPRA NO: ME-18 | DNR NO: ME-18 |
PROJECT TYPE: Shoreline Protection | NET ACRES BENEFITTED: 256 |
REGION: 4 | BASIN: Mermentau | PARISH: Cameron |
LEAD AGENCY: NMFS |
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA |
MILESTONES:
CSA EXECUTION: | 27-Sep-2001 | ( Actual ) | ||
DESIGN COMPLETION: | 07-Nov-2005 | ( Actual ) | ||
CONSTRUCTION START: | 01-Nov-2017 | ( Actual ) | ||
CONSTRUCTION COMPLETION: | 27-May-2020 | ( Actual ) | ||
ESCROW AMENDMENT | 19-Aug-2011 | ( Actual ) | No: | 94 |
MONITORING PLAN APPROVAL: | ||||
O and M PLAN APPROVAL: | ||||
DEAUTHORIZATION DATE: | ||||
CASH FLOW PROECTS: | ||||
Phase 1 Approval: | 10-Jan-2001 | ( Actual ) | ||
Phase 2 Approval: | 22-Jan-2016 | ( Actual ) |
LEGISLATIVE DISTRICTS:
CONGRESSIONAL DISTRICT: | 3 | Charles W. Boustany |
STATE SENATE DISTRICT: | 25 | Dan "Blade" Morrish |
STATE HOUSE DISTRICT: | 47 | Bob Hensgens |
Point of Contact:
DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE
John Foret 646 Cajundome Boulevard Lafayette, LA 70506 |
|
PROJECT STATUS REPORT as of 21-Nov-2024
Rockefeller Refuge Gulf Shoreline Stabilization
PROJECT LOCATION:
The project is located along the Rockefeller Refuge Gulf shoreline from the western side of Joseph's Harbor west for approximately 4 miles in Cameron Parish, LA.
PROJECT DESCRIPTION:
The project addressed Rockefeller Refuge Gulf shoreline retreat which averages approximately 46 feet per year with subsequent direct loss of saline marsh. The project entailed construction of a nearshore breakwater along the Gulf of Mexico shoreline, extending approximately four miles from Joseph's Harbor westward. The proposed feature incorporated one of the previously constructed ME-18 test-sections and LA-08 Demonstration project features. The structure was tied into the west bank of Joseph Harbor, using encapsulated light weight aggregate overtopped with large stone. It was designed to attenuate shoreline retreat along this stretch of Gulf shoreline, as well as promote shallowing, settling out, and natural vegetative colonization of over wash material landward of the proposed structure.
PROJECT STATUS: (Project Status Last Updated: 09-Jun-2021 )
The bid opening was on July 9, 2017 and the construction contract was awarded to Leblanc Marine, LLC. The pre-construction meeting was held on October 4, 2017 and the notice to proceed was issued on November 1, 2017. Mobilization for construction began on April 21, 2018 and the project was accepted on May 27, 2020. A total of 266,962 tons of armor stone; 43,106 tons of bedding stone; 62,815 cubic yards of lightweight aggregate; and 181,780 square yards of geotextile fabric were installed. A total of 20,352 linear feet of breakwater were installed along the Gulf of Mexico shoreline of Rockefeller Refuge.
FUND STATUS:
The current project estimate is $33,463,579 , which includes $33,099,991 for construction first costs, and $208,479 and $155,109 for 20 years of monitoring and operations and maintenance, respectively.
LaCoast.gov | Project Managers' Technical Factsheet |