PROJECT STATUS REPORT as of 22-Nov-2024
PROJECT DATA
PROJECT: Grand Lake Shoreline Protection |
PRIORITY LIST: 11 | PROJECT NO: 1103 | CWPPRA NO: ME-21a | DNR NO: ME-21 |
PROJECT TYPE: Shoreline Protection | NET ACRES BENEFITTED: 45 |
REGION: 4 | BASIN: Mermentau | PARISH: Cameron |
LEAD AGENCY: NRCS |
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA |
MILESTONES:
CSA EXECUTION: | 20-Sep-2011 | ( Actual ) | ||
DESIGN COMPLETION: | 10-Aug-2004 | ( Actual ) | ||
CONSTRUCTION START: | 01-Dec-2016 | ( Actual ) | ||
CONSTRUCTION COMPLETION: | 07-Jul-2017 | ( Actual ) | ||
ESCROW AMENDMENT | No: | |||
MONITORING PLAN APPROVAL: | 11-May-2005 | ( Actual ) | ||
O and M PLAN APPROVAL: | ||||
DEAUTHORIZATION DATE: | ||||
CASH FLOW PROECTS: | ||||
Phase 1 Approval: | 16-Jan-2002 | ( Actual ) | ||
Phase 2 Approval: | 15-Feb-2007 | ( Actual ) |
LEGISLATIVE DISTRICTS:
CONGRESSIONAL DISTRICT: | 7 | Not Available |
STATE SENATE DISTRICT: | 25 | Dan "Blade" Morrish |
STATE HOUSE DISTRICT: | 47 | Bob Hensgens |
Point of Contact:
DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE
Quin Kinler Denham Springs, LA |
|
PROJECT STATUS REPORT as of 22-Nov-2024
Grand Lake Shoreline Protection
PROJECT LOCATION:
The project is located in Region 4, Mermentau Basin, Cameron Parish. This project is located along the southern shoreline of Grand Lake between Superior Canal and Tebo Point.
PROJECT DESCRIPTION:
A portion of this project was built under the CIAP Program. The CWPPRA construction portion of this project is approximately 5,700 feet of foreshore rock dike.
PROJECT STATUS: (Project Status Last Updated: 22-Sep-2017 )
Construction completed 7/7/2017.
FUND STATUS:
The current project estimate is $5,164,297 , which includes $5,071,412 for construction first costs, and $2,313 and $90,572 for 20 years of monitoring and operations and maintenance, respectively.