COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 03-Dec-2024

Southwest LA Gulf Shoreline Nourish &Protect TRANSFER

PROJECT DATA

PROJECT: Southwest LA Gulf Shoreline Nourish &Protect TRANSFER
PRIORITY LIST: 16 PROJECT NO: 1602 CWPPRA NO: ME-24 DNR NO: ME-24
PROJECT TYPE: Shoreline Protection NET ACRES BENEFITTED: 888
REGION: 4 BASIN: Mermentau PARISH: Cameron
LEAD AGENCY: COE
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA

MILESTONES:

CSA EXECUTION:    
DESIGN COMPLETION:    
CONSTRUCTION START: 6/30/2017 12:00:00 AM *    
CONSTRUCTION COMPLETION: 7/10/2018 12:00:00 AM *    
ESCROW AMENDMENT No:
MONITORING PLAN APPROVAL:    
O and M PLAN APPROVAL:    
DEAUTHORIZATION DATE:      
CASH FLOW PROECTS:        
Phase 1 Approval: 18-Oct-2006 ( Actual )    
Phase 2 Approval: 20-Jan-2017 *    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT: 3 Charles W. Boustany
STATE SENATE DISTRICT: 999 Not Available
STATE HOUSE DISTRICT: 999 Not Available

Point of Contact:

DEPT. OF THE ARMY
CORPS OF ENGINEERS

Susan Hennington
Biologist
CEMVN-PM-OR
7400 Leake Avenue
New Orleans, LA 70160-0267
PHONES:  
Office: (504) 862-2504
Fax: (504) 862-1892

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 03-Dec-2024

Southwest LA Gulf Shoreline Nourish &Protect TRANSFER

PROJECT LOCATION:

PROJECT DESCRIPTION:


PROJECT STATUS: (Project Status Last Updated: 18-Jun-2014 )

This project was approved for Phase 1 design in Oct 2006. The COE internal project delivery team (PDT) has been assembled. Upon attainment of a Cost Share Agreement with CPRA, a Phase 1 work plan will be developed and a kickoff meeting/site visit scheduled. In Mar 2009, a project Fact Sheet and map was approved by the New Orleans District for placement on the LaCoast website. At this time, the project is unable to be further developed by the COE and the CPRA until a Cost Share Agreement is signed.

FUND STATUS:

The current project estimate is $11,594 , which includes $11,594 for construction first costs, and $0 and $0 for 20 years of monitoring and operations and maintenance, respectively.

LaCoast.gov Project Managers' Technical Factsheet