PROJECT STATUS REPORT as of 03-Dec-2024
PROJECT DATA
PROJECT: LaBranche Central Marsh Creation |
PRIORITY LIST: 21 | PROJECT NO: 2102 | CWPPRA NO: 33 | DNR NO: PO-133 |
PROJECT TYPE: Marsh Creation | NET ACRES BENEFITTED: 668 |
REGION: 1 | BASIN: Pontchartrain | PARISH: St. Charles |
LEAD AGENCY: NRCS |
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA |
MILESTONES:
CSA EXECUTION: | 01-Jun-2012 | ( Actual ) | ||
DESIGN COMPLETION: | 1/21/2018 12:00:00 AM | * | ||
CONSTRUCTION START: | 9/1/2018 12:00:00 AM | * | ||
CONSTRUCTION COMPLETION: | 9/1/2020 12:00:00 AM | * | ||
ESCROW AMENDMENT | No: | |||
MONITORING PLAN APPROVAL: | ||||
O and M PLAN APPROVAL: | ||||
DEAUTHORIZATION DATE: | ||||
CASH FLOW PROECTS: | ||||
Phase 1 Approval: | 19-Jan-2012 | ( Actual ) | ||
Phase 2 Approval: | 21-Jan-2018 | * |
LEGISLATIVE DISTRICTS:
CONGRESSIONAL DISTRICT: | 6 | William Cassidy |
STATE SENATE DISTRICT: | 999 | Not Available |
STATE HOUSE DISTRICT: | 999 | Not Available |
Point of Contact:
DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE
Quin Kinler Denham Springs, LA |
|
PROJECT STATUS REPORT as of 03-Dec-2024
LaBranche Central Marsh Creation
PROJECT LOCATION:
PROJECT DESCRIPTION:
PROJECT STATUS: (Project Status Last Updated: 22-Sep-2017 )
Revised Scheduled Dates: 30% Review Jan 2018; 95% Review July 2018; Contracting April 2019; Construction Start September 2019
FUND STATUS:
The current project estimate is $3,885,298 , which includes $3,885,298 for construction first costs, and $0 and $0 for 20 years of monitoring and operations and maintenance, respectively.