COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 26-Apr-2024

Fritchie Marsh Creation and Terracing

PROJECT DATA

PROJECT: Fritchie Marsh Creation and Terracing
PRIORITY LIST: 25 PROJECT NO: CWPPRA NO: PO-173 DNR NO: PO-173
PROJECT TYPE: Marsh Creation NET ACRES BENEFITTED: 290
REGION: 1 BASIN: Pontchartrain PARISH: St. Tammany
LEAD AGENCY: NMFS
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA.

MILESTONES:

CSA EXECUTION:    
DESIGN COMPLETION:    
CONSTRUCTION START:    
CONSTRUCTION COMPLETION:    
ESCROW AMENDMENT No:
MONITORING PLAN APPROVAL:    
O and M PLAN APPROVAL:    
DEAUTHORIZATION DATE:      
CASH FLOW PROECTS:        
Phase 1 Approval: 21-Jan-2016 ( Actual )    
Phase 2 Approval:    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT:
STATE SENATE DISTRICT:
STATE HOUSE DISTRICT:

Point of Contact:

DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE

Donna Rogers



,  
PHONES:  
Office:
Fax:

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 26-Apr-2024

Fritchie Marsh Creation and Terracing

PROJECT LOCATION:

PROJECT DESCRIPTION:


PROJECT STATUS: (Project Status Last Updated: )

FUND STATUS:

The current project estimate is $3,033,294 , which includes $3,033,294 for construction first costs, and $0 and $0 for 20 years of monitoring and operations and maintenance, respectively.

LaCoast.gov Project Managers' Technical Factsheet