COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 23-Apr-2024

Bayou Cane Marsh Creation

PROJECT DATA

PROJECT: Bayou Cane Marsh Creation
PRIORITY LIST: 27 PROJECT NO: CWPPRA NO: PO-181 DNR NO: PO-181
PROJECT TYPE: Marsh Creation NET ACRES BENEFITTED: 557
REGION: 1 BASIN: Pontchartrain PARISH: St. Tammany
LEAD AGENCY: FWS
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA

MILESTONES:

CSA EXECUTION:    
DESIGN COMPLETION:    
CONSTRUCTION START:    
CONSTRUCTION COMPLETION:    
ESCROW AMENDMENT No:
MONITORING PLAN APPROVAL:    
O and M PLAN APPROVAL:    
DEAUTHORIZATION DATE:      
CASH FLOW PROECTS:        
Phase 1 Approval: 09-Feb-2018 ( Actual )    
Phase 2 Approval:    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT:
STATE SENATE DISTRICT:
STATE HOUSE DISTRICT:

Point of Contact:

DEPT. OF THE INTERIOR
FISH & WILDLIFE SERVICE

Darryl Clark
Senior Field Biologist
200 Dulles Dr.

Lafayette, LA 70506
PHONES:  
Office: (337) 291-3111
Fax: (337) 291-3139

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 23-Apr-2024

Bayou Cane Marsh Creation

PROJECT LOCATION:

PROJECT DESCRIPTION:


PROJECT STATUS: (Project Status Last Updated: )

FUND STATUS:

The current project estimate is $39,888,363 , which includes $38,693,254 for construction first costs, and $199,574 and $995,535 for 20 years of monitoring and operations and maintenance, respectively.

LaCoast.gov Project Managers' Technical Factsheet