COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 22-Nov-2024

MRGO Disposal Area Marsh Protection COMPLETE

PROJECT DATA

PROJECT: MRGO Disposal Area Marsh Protection COMPLETE
PRIORITY LIST: 3 PROJECT NO: 0330 CWPPRA NO: XPO-71 DNR NO: PO-19
PROJECT TYPE: Marsh Creation NET ACRES BENEFITTED: 755
REGION: 1 BASIN: Pontchartrain PARISH: St. Bernard
LEAD AGENCY: COE
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA.

MILESTONES:

CSA EXECUTION: 17-Jan-1997 ( Actual )    
DESIGN COMPLETION: 21-Apr-1998 ( Actual )    
CONSTRUCTION START: 25-Jan-1999 ( Actual )    
CONSTRUCTION COMPLETION: 29-Jan-1999 ( Actual )    
ESCROW AMENDMENT 13-Mar-1997 ( Actual ) No: 43
MONITORING PLAN APPROVAL:    
O and M PLAN APPROVAL:    
DEAUTHORIZATION DATE:      
CASH FLOW PROECTS:        
Phase 1 Approval: 01-Oct-1993 ( Actual )    
Phase 2 Approval:    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT: 1 Steve Scalise
STATE SENATE DISTRICT: 1 A. G. Crowe
STATE HOUSE DISTRICT: 103 Raymond E. Garofalo

Point of Contact:

DEPT. OF THE ARMY
CORPS OF ENGINEERS

Brad Inman
Project Manager
CEMVN-PM-OR
7400 Leake Avenue
New Orleans, LA 70160
PHONES:  
Office: (504) 862-1940
Fax: (504) 862-1892

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 22-Nov-2024

MRGO Disposal Area Marsh Protection COMPLETE

PROJECT LOCATION:

PROJECT DESCRIPTION:

The objective of the project is to protect and preserve vegetated wetlands by repairing the lateral and rear dikes of the MRGO disposal areas. Dike repairs, in conjunction with the installation of metal box weirs to control and divert water flow, will prevent the perched marshes from draining and becoming vegetated with upland plants. The project area is segmented into three separate reaches with each reach representing a fresh water marsh area. Approximately 28,000 linear feet of dike will be repaired. Metal box weirs with a single 40-inch pipe would be installed in the rear dikes at designated locations to control water levels within each area.

PROJECT STATUS: (Project Status Last Updated: 17-Jun-2002 )

Completed scope of work greatly reduced. Work was to be performed via a simplified acquisition contract as estimated construction cost is under $100,000. Bids received were higher than Government estimate by 25%. Subsequently received an in-house labor estimate from Vicksburg District. Vicksburg District completed construction on 29 January 1999. Cost increase was due to additional project management costs, environmental investigations and local sponsor activities not included in the baseline estimate. Further title research indicates that private ownership titles are unclear, requiring condemnation. This accounts for the long period between CSA execution and project construction.

FUND STATUS:

The current project estimate is $318,445 , which includes $292,134 for construction first costs, and $26,311 and $0 for 20 years of monitoring and operations and maintenance, respectively.

LaCoast.gov Project Managers' Technical Factsheet