PROJECT STATUS REPORT as of 12-Jun-2026
PROJECT DATA
| PROJECT: Lake Borgne and MRGO Shoreline Protection DEAUTHORIZED |
| PRIORITY LIST: 12 | PROJECT NO: 1204 | CWPPRA NO: PO-32 | DNR NO: PO-32 |
| PROJECT TYPE: Shoreline Protection | NET ACRES BENEFITTED: |
| REGION: 1 | BASIN: Pontchartrain | PARISH: St. Bernard |
| LEAD AGENCY: COE |
| LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA |
MILESTONES:
| CSA EXECUTION: | ||||
| DESIGN COMPLETION: | ||||
| CONSTRUCTION START: | ||||
| CONSTRUCTION COMPLETION: | ||||
| ESCROW AMENDMENT | No: | |||
| MONITORING PLAN APPROVAL: | ||||
| O and M PLAN APPROVAL: | ||||
| DEAUTHORIZATION DATE: | 23-Jun-2010 | |||
| CASH FLOW PROECTS: | ||||
| Phase 1 Approval: | 16-Jan-2003 | ( Actual ) | ||
| Phase 2 Approval: |
LEGISLATIVE DISTRICTS:
| CONGRESSIONAL DISTRICT: | 1 | Steve Scalise |
| STATE SENATE DISTRICT: | 1 | A. G. Crowe |
| STATE HOUSE DISTRICT: | 103 | Raymond E. Garofalo |
Point of Contact:
DEPT. OF THE ARMY
CORPS OF ENGINEERS
|
Brad Inman Project Manager CEMVN-PM-OR 7400 Leake Avenue New Orleans, LA 70160 |
|
PROJECT STATUS REPORT as of 12-Jun-2026
Lake Borgne and MRGO Shoreline Protection DEAUTHORIZED
PROJECT LOCATION:
PROJECT DESCRIPTION:
PROJECT STATUS: (Project Status Last Updated: )
FUND STATUS:
The current project estimate is $1,089,193 , which includes $1,088,658 for construction first costs, and $535 and $0 for 20 years of monitoring and operations and maintenance, respectively.
| LaCoast.gov | Project Managers' Technical Factsheet |