PROJECT STATUS REPORT as of 21-Nov-2024
PROJECT DATA
PROJECT: n |
PRIORITY LIST: 16 | PROJECT NO: 1601 | CWPPRA NO: PO-34 | DNR NO: PO-34 |
PROJECT TYPE: Marsh Creation | NET ACRES BENEFITTED: 181 |
REGION: 1 | BASIN: Pontchartrain | PARISH: Orleans |
LEAD AGENCY: NRCS |
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA |
MILESTONES:
CSA EXECUTION: | 11-Jun-2008 | ( Actual ) | ||
DESIGN COMPLETION: | 15-Nov-2011 | ( Actual ) | ||
CONSTRUCTION START: | ||||
CONSTRUCTION COMPLETION: | ||||
ESCROW AMENDMENT | No: | |||
MONITORING PLAN APPROVAL: | ||||
O and M PLAN APPROVAL: | ||||
DEAUTHORIZATION DATE: | ||||
CASH FLOW PROECTS: | ||||
Phase 1 Approval: | 18-Oct-2006 | ( Actual ) | ||
Phase 2 Approval: |
LEGISLATIVE DISTRICTS:
CONGRESSIONAL DISTRICT: | 1 | Steve Scalise |
STATE SENATE DISTRICT: | 999 | Not Available |
STATE HOUSE DISTRICT: | 999 | Not Available |
Point of Contact:
DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE
Quin Kinler Denham Springs, LA |
|
PROJECT STATUS REPORT as of 21-Nov-2024
n
PROJECT LOCATION:
PROJECT DESCRIPTION:
PROJECT STATUS: (Project Status Last Updated: 19-Nov-2014 )
Project has been placed on Inactive list until CWPPRA is reauthorized, receives further funding, or another program is found that can provided construction funding.
FUND STATUS:
The current project estimate is $1,364,230 , which includes $1,364,230 for construction first costs, and $0 and $0 for 20 years of monitoring and operations and maintenance, respectively.