PROJECT STATUS REPORT as of 22-Nov-2024
PROJECT DATA
PROJECT: Vegetative Plantings - Timbalier Island Planting Demo COMPLETE |
PRIORITY LIST: 1 | PROJECT NO: 0107-3 | CWPPRA NO: TE-18 | DNR NO: TE-18 |
PROJECT TYPE: Vegetative Plantings | NET ACRES BENEFITTED: 0 |
REGION: 3 | BASIN: Terrebonne | PARISH: Terrebonne |
LEAD AGENCY: NRCS |
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA. |
MILESTONES:
CSA EXECUTION: | 17-Apr-1993 | ( Actual ) | ||
DESIGN COMPLETION: | 15-Aug-1994 | ( Actual ) | ||
CONSTRUCTION START: | 15-Mar-1995 | ( Actual ) | ||
CONSTRUCTION COMPLETION: | 30-Jul-1996 | ( Actual ) | ||
ESCROW AMENDMENT | 13-Jun-1994 | ( Actual ) | No: | 7 |
MONITORING PLAN APPROVAL: | 21-Jun-1995 | ( Actual ) | ||
O and M PLAN APPROVAL: | ||||
DEAUTHORIZATION DATE: | ||||
CASH FLOW PROECTS: | ||||
Phase 1 Approval: | 31-Oct-1991 | ( Actual ) | ||
Phase 2 Approval: |
LEGISLATIVE DISTRICTS:
CONGRESSIONAL DISTRICT: | 1 | Steve Scalise |
STATE SENATE DISTRICT: | 20 | Norby Chabert |
STATE HOUSE DISTRICT: | 53 | Lenar L. Whitney |
Point of Contact:
DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE
Quin Kinler Denham Springs, LA |
|
PROJECT STATUS REPORT as of 22-Nov-2024
Vegetative Plantings - Timbalier Island Planting Demo COMPLETE
PROJECT LOCATION:
PROJECT DESCRIPTION:
Sand fences will be installed and vegetation suited to the salinity and habitat type of Timbalier Island will be planted in several areas on the Island to trap sand and buffer wind and wave energy.
PROJECT STATUS: (Project Status Last Updated: 01-Jan-1990 )
Sub-project of the Vegetative Plantings project. Complete.
FUND STATUS:
The current project estimate is $300,492 , which includes $196,251 for construction first costs, and $91,193 and $13,048 for 20 years of monitoring and operations and maintenance, respectively.
LaCoast.gov | Project Managers' Technical Factsheet |