PROJECT STATUS REPORT as of 04-Oct-2024
PROJECT DATA
PROJECT: Lake Chapeau Sediment Input and Hydrologic Restoration COMPLETE |
PRIORITY LIST: 3 | PROJECT NO: 0342 | CWPPRA NO: PTE-23 | DNR NO: TE-26 |
PROJECT TYPE: Marsh Creation | NET ACRES BENEFITTED: 509 |
REGION: 3 | BASIN: Terrebonne | PARISH: Terrebonne |
LEAD AGENCY: NMFS |
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA. |
MILESTONES:
CSA EXECUTION: | 01-Mar-1995 | ( Actual ) | ||
DESIGN COMPLETION: | 15-Feb-1998 | ( Actual ) | ||
CONSTRUCTION START: | 14-Sep-1998 | ( Actual ) | ||
CONSTRUCTION COMPLETION: | 18-May-1999 | ( Actual ) | ||
ESCROW AMENDMENT | 18-May-1995 | ( Actual ) | No: | 21 |
MONITORING PLAN APPROVAL: | ||||
O and M PLAN APPROVAL: | 28-Feb-2003 | ( Actual ) | ||
DEAUTHORIZATION DATE: | ||||
CASH FLOW PROECTS: | ||||
Phase 1 Approval: | 01-Oct-1993 | ( Actual ) | ||
Phase 2 Approval: | 05-Nov-2008 | ( Actual ) |
LEGISLATIVE DISTRICTS:
CONGRESSIONAL DISTRICT: | 1 | Steve Scalise |
STATE SENATE DISTRICT: | 20 | Norby Chabert |
STATE HOUSE DISTRICT: | 51 | Joe Harrison |
Point of Contact:
DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE
John Foret 646 Cajundome Boulevard Lafayette, LA 70506 |
|
PROJECT STATUS REPORT as of 04-Oct-2024
Lake Chapeau Sediment Input and Hydrologic Restoration COMPLETE
PROJECT LOCATION:
The project area incorporates the western central portion of Point au Fer Island, located in the extreme southwestern corner of Terrebonne Parish, and a portion of southeastern Atchafalaya Bay.
PROJECT DESCRIPTION:
Generally, the rate of wetland loss on Point au Fer Island is decreasing due to sediment and freshwater input from Atchafalaya Bay; however, these processes are being defeated in the Lake Chapeau area by the presence of tidal circulation between Four League Bay and the southeastern portion of Atchafalaya Bay. Major marsh loss has occurred in the area surrounding Lake Chapeau and continues to occur at a rate of nearly 15 acres per year. The continuation of these processes will result in the disappearance of the vital land bridge in the Chapeau area. The objectives of the project are to restore the marshes west of Lake Chapeau, reestablishing the hydrologic separation of the Locust Bayou and Alligator Bayou watersheds, and to reestablish the natural drainage patterns within the Lake Chapeau area.
PROJECT STATUS: (Project Status Last Updated: 29-Aug-2011 )
Maintenance event to degrade the project feature identified as Weir 3 began on 4/27/2011, and the work was accepted on 6/24/2011.
FUND STATUS:
The current project estimate is $6,199,560 , which includes $4,202,155 for construction first costs, and $881,973 and $1,115,432 for 20 years of monitoring and operations and maintenance, respectively.
LaCoast.gov | Project Managers' Technical Factsheet |