COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 03-Dec-2024

Raccoon Island Breakwaters Demo COMPLETE

PROJECT DATA

PROJECT: Raccoon Island Breakwaters Demo COMPLETE
PRIORITY LIST: 5 PROJECT NO: 0561 CWPPRA NO: PTE-15bii DNR NO: TE-29
PROJECT TYPE: Shoreline Protection NET ACRES BENEFITTED: 0
REGION: 3 BASIN: Terrebonne PARISH: Terrebonne
LEAD AGENCY: NRCS
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA.

MILESTONES:

CSA EXECUTION: 03-Sep-1996 ( Actual )    
DESIGN COMPLETION: 01-Dec-1996 ( Actual )    
CONSTRUCTION START: 21-Apr-1997 ( Actual )    
CONSTRUCTION COMPLETION: 31-Jul-1997 ( Actual )    
ESCROW AMENDMENT 06-Dec-1996 ( Actual ) No: 39
MONITORING PLAN APPROVAL: 24-Apr-1997 ( Actual )    
O and M PLAN APPROVAL:    
DEAUTHORIZATION DATE:      
CASH FLOW PROECTS:        
Phase 1 Approval: 28-Feb-1996 ( Actual )    
Phase 2 Approval:    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT: 1 Steve Scalise
STATE SENATE DISTRICT: 20 Norby Chabert
STATE HOUSE DISTRICT: 53 Lenar L. Whitney

Point of Contact:

DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE

Quin Kinler



Denham Springs, LA 
PHONES:  
Office:
Fax:

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 03-Dec-2024

Raccoon Island Breakwaters Demo COMPLETE

PROJECT LOCATION:

PROJECT DESCRIPTION:

The project will protect the newly refurbished beaches and wetlands of Raccoon Island and protect back barrier and mainland marshes with six segmented breakwaters.

PROJECT STATUS: (Project Status Last Updated: 01-Jan-1990 )

Complete.

FUND STATUS:

The current project estimate is $1,751,046 , which includes $1,573,970 for construction first costs, and $162,804 and $14,272 for 20 years of monitoring and operations and maintenance, respectively.