COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 19-Apr-2024

Timbalier Island Dune & Marsh Restoration

PROJECT DATA

PROJECT: Timbalier Island Dune & Marsh Restoration
PRIORITY LIST: 9 PROJECT NO: 0907 CWPPRA NO: XTE-45a DNR NO: TE-40
PROJECT TYPE: Barrier Island NET ACRES BENEFITTED: 273
REGION: 3 BASIN: Terrebonne PARISH: Terrebonne
LEAD AGENCY: EPA
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA

MILESTONES:

CSA EXECUTION: 05-Oct-2000 ( Actual )    
DESIGN COMPLETION:    
CONSTRUCTION START: 01-Jun-2004 ( Actual )    
CONSTRUCTION COMPLETION: 19-Mar-2009 ( Actual )    
ESCROW AMENDMENT 02-Mar-2001 ( Actual ) No: 84
MONITORING PLAN APPROVAL: 25-Jun-2007 ( Actual )    
O and M PLAN APPROVAL:    
DEAUTHORIZATION DATE:      
CASH FLOW PROECTS:        
Phase 1 Approval: 11-Jan-2000 ( Actual )    
Phase 2 Approval: 16-Jan-2003 ( Actual )    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT: 1 Steve Scalise
STATE SENATE DISTRICT: 20 Norby Chabert
STATE HOUSE DISTRICT: 53 Lenar L. Whitney

Point of Contact:

ENVIRONMENTAL PROTECTION AGENCY
REGION 6

Patricia Taylor

EPA Region 6 (6WD-AM)
1201 Elm Street, Suite 500
Dallas, TX 75270
PHONES:  
Office: (214) 665-6403
Fax:

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 19-Apr-2024

Timbalier Island Dune & Marsh Restoration

PROJECT LOCATION:

Project is located on the eastern end of Timbalier Island, Terrebonne Parish, LA.

PROJECT DESCRIPTION:

Construction will include beach, dune, and marsh creation. Sediment source alternatives are being developed and evaluated during design.

PROJECT STATUS: (Project Status Last Updated: 27-Aug-2009 )

Lessoned learned meeting was held on April 23, 2008. LDNR grant for Phase II construction activities was closed-out on March 19, 2009. Remaining Phase II increment activities included on-going annual inspections.

FUND STATUS:

The current project estimate is $16,175,513 , which includes $15,771,447 for construction first costs, and $224,887 and $179,179 for 20 years of monitoring and operations and maintenance, respectively.

LaCoast.gov Project Managers' Technical Factsheet