PROJECT STATUS REPORT as of 26-Dec-2024
PROJECT DATA
PROJECT: GIWW Bank Restoration of Critical Areas in Terrebonne |
PRIORITY LIST: 10 | PROJECT NO: 1012 | CWPPRA NO: TE-43 | DNR NO: TE-43 |
PROJECT TYPE: Shoreline Protection | NET ACRES BENEFITTED: 64 |
REGION: 3 | BASIN: Terrebonne | PARISH: Terrebonne |
LEAD AGENCY: NRCS |
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA |
MILESTONES:
CSA EXECUTION: | 16-May-2001 | ( Actual ) | ||
DESIGN COMPLETION: | 10/1/2004 12:00:00 AM | * | ||
CONSTRUCTION START: | 02-May-2013 | ( Actual ) | ||
CONSTRUCTION COMPLETION: | 01-Feb-2014 | ( Actual ) | ||
ESCROW AMENDMENT | 21-May-2002 | ( Actual ) | No: | 100 |
MONITORING PLAN APPROVAL: | ||||
O and M PLAN APPROVAL: | ||||
DEAUTHORIZATION DATE: | ||||
CASH FLOW PROECTS: | ||||
Phase 1 Approval: | 10-Jan-2001 | ( Actual ) | ||
Phase 2 Approval: | 20-Jan-2010 | ( Actual ) |
LEGISLATIVE DISTRICTS:
CONGRESSIONAL DISTRICT: | 6 | William Cassidy |
STATE SENATE DISTRICT: | 21 | R. L. "Bret" Allain II |
STATE HOUSE DISTRICT: | 51 | Joe Harrison |
Point of Contact:
DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE
Quin Kinler Denham Springs, LA |
|
PROJECT STATUS REPORT as of 26-Dec-2024
GIWW Bank Restoration of Critical Areas in Terrebonne
PROJECT LOCATION:
This project is located along the GIWW in western Terrebonne Parish.
PROJECT DESCRIPTION:
This project will restore critical lengths of deteriorated channel banks, and stabilize/armor selected critical lengths of deteriorated channel banks with hard shoreline stabilization materials.
PROJECT STATUS: (Project Status Last Updated: 11-Jul-2012 )
CPRA assigned land rights to NRCS in April 2012. Project re-surveyed to verify design was still current. Project is scheduled for construction in December 2012.
FUND STATUS:
The current project estimate is $10,916,662 , which includes $9,332,533 for construction first costs, and $14,954 and $1,569,175 for 20 years of monitoring and operations and maintenance, respectively.
LaCoast.gov | Project Managers' Technical Factsheet |