PROJECT STATUS REPORT as of 21-Nov-2024
PROJECT DATA
PROJECT: Ship Shoal: Whiskey West Flank Restoration DEAUTHORIZED |
PRIORITY LIST: 11 | PROJECT NO: 1105 | CWPPRA NO: TE-14-1 | DNR NO: TE-47 |
PROJECT TYPE: Barrier Island | NET ACRES BENEFITTED: |
REGION: 3 | BASIN: Terrebonne | PARISH: Terrebonne |
LEAD AGENCY: EPA |
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA |
MILESTONES:
CSA EXECUTION: | 17-Mar-2003 | ( Actual ) | ||
DESIGN COMPLETION: | 29-Sep-2005 | ( Actual ) | ||
CONSTRUCTION START: | ||||
CONSTRUCTION COMPLETION: | ||||
ESCROW AMENDMENT | No: | |||
MONITORING PLAN APPROVAL: | ||||
O and M PLAN APPROVAL: | ||||
DEAUTHORIZATION DATE: | 29-Jan-2021 | |||
CASH FLOW PROECTS: | ||||
Phase 1 Approval: | 16-Jan-2002 | ( Actual ) | ||
Phase 2 Approval: | 23-Jan-2013 | * |
LEGISLATIVE DISTRICTS:
CONGRESSIONAL DISTRICT: | 1 | Steve Scalise |
STATE SENATE DISTRICT: | 20 | Norby Chabert |
STATE HOUSE DISTRICT: | 52 | Gordon Dove |
Point of Contact:
ENVIRONMENTAL PROTECTION AGENCY
REGION 6
Brad Crawford Project Manager EPA Region 6 (6WQ-EMC) 1445 Ross Ave. Dallas, TX 75202-2733 |
|
PROJECT STATUS REPORT as of 21-Nov-2024
Ship Shoal: Whiskey West Flank Restoration DEAUTHORIZED
PROJECT LOCATION:
Western end of Whiskey Island of the Isles Dernieres Chain of Barrier Islands, Terrebonne Parish, LA
PROJECT DESCRIPTION:
Mine and transport sand approximately 8 miles from the "Ship Shoal" offshore sand body to rebuild dunes and marsh platform.
PROJECT STATUS: (Project Status Last Updated: 21-Jan-2013 )
Phase 2 funding was reqeusted, but not recommended, at the December 2012 Technical Committee Meeting. Sponsors will determine whether future Phase 2 requests will be made.
FUND STATUS:
The current project estimate is $2,298,822 , which includes $2,290,609 for construction first costs, and $8,213 and $0 for 20 years of monitoring and operations and maintenance, respectively.
LaCoast.gov | Project Managers' Technical Factsheet |