PROJECT STATUS REPORT as of 03-Dec-2024
PROJECT DATA
PROJECT: Raccoon Island Shoreline Protection/Marsh Creation |
PRIORITY LIST: 11 | PROJECT NO: 1114 | CWPPRA NO: TE-14-2 | DNR NO: TE-48 |
PROJECT TYPE: Barrier Island | NET ACRES BENEFITTED: 71 |
REGION: 3 | BASIN: Terrebonne | PARISH: Terrebonne |
LEAD AGENCY: NRCS |
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA |
MILESTONES:
CSA EXECUTION: | 23-Apr-2002 | ( Actual ) | ||
DESIGN COMPLETION: | 12/1/2008 12:00:00 AM | * | ||
CONSTRUCTION START: | 13-Dec-2005 | ( Actual ) | ||
CONSTRUCTION COMPLETION: | 27-Apr-2013 | ( Actual ) | ||
ESCROW AMENDMENT | 27-Oct-2003 | ( Actual ) | No: | 107 |
MONITORING PLAN APPROVAL: | ||||
O and M PLAN APPROVAL: | ||||
DEAUTHORIZATION DATE: | ||||
CASH FLOW PROECTS: | ||||
Phase 1 Approval: | 16-Jan-2002 | ( Actual ) | ||
Phase 2 Approval: | 13-Oct-2004 | ( Actual ) |
LEGISLATIVE DISTRICTS:
CONGRESSIONAL DISTRICT: | 1 | Steve Scalise |
STATE SENATE DISTRICT: | 20 | Norby Chabert |
STATE HOUSE DISTRICT: | 53 | Lenar L. Whitney |
Point of Contact:
DEPT. OF COMMERCE
NATIONAL MARINE FISHERIES SERVICE
Quin Kinler Denham Springs, LA |
|
PROJECT STATUS REPORT as of 03-Dec-2024
Raccoon Island Shoreline Protection/Marsh Creation
PROJECT LOCATION:
This project is located on Raccoon Island in Terrebonne Parish
PROJECT DESCRIPTION:
Eight segmented breakwaters will be installed along the gulf side of the island and dredged sediment will be used to create marsh on the land side of the island.
PROJECT STATUS: (Project Status Last Updated: 10-Dec-2014 )
Phase A construction began on 12/12/2005 Phase A construction ended on 9/16/2007 Phase B construction began on 9/27/2012 Phase B construction ended on 4/23/2103
FUND STATUS:
The current project estimate is $20,880,030 , which includes $17,529,904 for construction first costs, and $420,444 and $2,929,682 for 20 years of monitoring and operations and maintenance, respectively.