COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 28-Mar-2024

Avoca Island Diversion DEAUTHORIZED

PROJECT DATA

PROJECT: Avoca Island Diversion DEAUTHORIZED
PRIORITY LIST: 12 PROJECT NO: 1201 CWPPRA NO: TE-49 DNR NO: TE-49
PROJECT TYPE: Sediment Diversion NET ACRES BENEFITTED:
REGION: 3 BASIN: Terrebonne PARISH: St. Mary
LEAD AGENCY: COE
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA

MILESTONES:

CSA EXECUTION:    
DESIGN COMPLETION: 11/7/2013 12:00:00 AM *    
CONSTRUCTION START:    
CONSTRUCTION COMPLETION:    
ESCROW AMENDMENT No:
MONITORING PLAN APPROVAL:    
O and M PLAN APPROVAL:    
DEAUTHORIZATION DATE: 04-Jun-2013      
CASH FLOW PROECTS:        
Phase 1 Approval: 16-Jan-2003 ( Actual )    
Phase 2 Approval:    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT: 3 Charles W. Boustany
STATE SENATE DISTRICT: 21 R. L. "Bret" Allain II
STATE HOUSE DISTRICT: 51 Joe Harrison

Point of Contact:

DEPT. OF THE ARMY
CORPS OF ENGINEERS

Susan Hennington
Biologist
CEMVN-PM-OR
7400 Leake Avenue
New Orleans, LA 70160-0267
PHONES:  
Office: (504) 862-2504
Fax: (504) 862-1892

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 28-Mar-2024

Avoca Island Diversion DEAUTHORIZED

PROJECT LOCATION:

The project is located in the Avoca Island area in St. Mary Parish, Louisiana.

PROJECT DESCRIPTION:


PROJECT STATUS: (Project Status Last Updated: 20-Jun-2014 )

The TE-49 Avoca Diversion and Land Building Project was deauthorized per CWPPRA Task Force decision on 4 June 2013.

FUND STATUS:

The current project estimate is $1,736,137 , which includes $1,735,097 for construction first costs, and $1,040 and $0 for 20 years of monitoring and operations and maintenance, respectively.

LaCoast.gov Project Managers' Technical Factsheet