MILESTONES:
CSA EXECUTION: | 29-Sep-2004 | ( Actual ) | ||
DESIGN COMPLETION: | 07-Nov-2007 | ( Actual ) | ||
CONSTRUCTION START: | 11-Feb-2009 | ( Actual ) | ||
CONSTRUCTION COMPLETION: | 18-Jun-2010 | ( Actual ) | ||
ESCROW AMENDMENT | No: | |||
MONITORING PLAN APPROVAL: | 05-Nov-2007 | ( Actual ) | ||
O and M PLAN APPROVAL: | 13-Nov-2007 | ( Actual ) | ||
DEAUTHORIZATION DATE: | ||||
CASH FLOW PROECTS: | ||||
Phase 1 Approval: | 28-Jan-2004 | ( Actual ) | ||
Phase 2 Approval: | 13-Feb-2008 | ( Actual ) |
LEGISLATIVE DISTRICTS:
CONGRESSIONAL DISTRICT: | 3 | Charles W. Boustany |
STATE SENATE DISTRICT: | 999 | Not Available |
STATE HOUSE DISTRICT: | 999 | Not Available |
Point of Contact:
ENVIRONMENTAL PROTECTION AGENCY
REGION 6
Brad Crawford Project Manager EPA Region 6 (6WQ-EMC) 1445 Ross Ave. Dallas, TX 75202-2733 |
|
PROJECT STATUS REPORT as of 26-Dec-2024
Whiskey Island Back Barrier Marsh Creation
PROJECT LOCATION:
Whiskey Island, which is one of the five islands that comprise the Isles Dernieres barrier island chain, is located 18 miles southwest of Cocodrie in Terrebonne Parish, Louisiana. It is bounded by Coupe Colin to the west, Whiskey Pass to the east, Lake Pelto, Caillou Boca, and Caillou Bay to the north, and the Gulf of Mexico to the south.
PROJECT DESCRIPTION:
The objective of the Whiskey Island Back Barrier Marsh Creation Project (TE-50) is to demonstrate on a small scale the ability to create a back barrier marsh platform on which a barrier island can migrate. Proposed project goals are to construct a sand dune along the gulf side beach shore, to create approximately 300 acres of back barrier intertidal habitat, and to construct a minimum of 10,000 linear feet of tidal creeks and six 1-acre tidal ponds to allow hydraulic exchange and circulation within the new back barrier marsh. Project goals are also to increase the longevity of the previously restored and natural portions of the island by increasing the island’s width, to maintain the longevity of the island by conserving sand volume and elevation by increasing the islands width, and to vegetate the completed project with smooth cordgrass.
PROJECT STATUS: (Project Status Last Updated: 21-Jan-2013 )
After further assessment of project vegetation, sponsors intend to pursue an additional vegetation planting event.
FUND STATUS:
The current project estimate is $26,167,668 , which includes $25,809,660 for construction first costs, and $251,261 and $106,747 for 20 years of monitoring and operations and maintenance, respectively.