PROJECT STATUS REPORT as of 11-Jun-2026
PROJECT DATA
| PROJECT: Vermilion River Cutoff Bank Protection COMPLETE |
| PRIORITY LIST: 1 | PROJECT NO: 0103 | CWPPRA NO: TV-03 | DNR NO: TV-03 |
| PROJECT TYPE: Shoreline Protection | NET ACRES BENEFITTED: 65 |
| REGION: 3 | BASIN: Teche / Vermilion | PARISH: Vermilion |
| LEAD AGENCY: COE |
| LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA. |
MILESTONES:
| CSA EXECUTION: | 17-Apr-1993 | ( Actual ) | ||
| DESIGN COMPLETION: | 31-May-1994 | ( Actual ) | ||
| CONSTRUCTION START: | 10-Jan-1996 | ( Actual ) | ||
| CONSTRUCTION COMPLETION: | 11-Feb-1996 | ( Actual ) | ||
| ESCROW AMENDMENT | 05-Jul-1995 | ( Actual ) | No: | 16 |
| MONITORING PLAN APPROVAL: | ||||
| O and M PLAN APPROVAL: | 22-May-2000 | ( Actual ) | ||
| DEAUTHORIZATION DATE: | ||||
| CASH FLOW PROECTS: | ||||
| Phase 1 Approval: | 31-Oct-1991 | ( Actual ) | ||
| Phase 2 Approval: |
LEGISLATIVE DISTRICTS:
| CONGRESSIONAL DISTRICT: | 3 | Charles W. Boustany |
| STATE SENATE DISTRICT: | 25 | Dan "Blade" Morrish |
| STATE HOUSE DISTRICT: | 47 | Bob Hensgens |
Point of Contact:
DEPT. OF THE ARMY
CORPS OF ENGINEERS
|
Bill Hicks Project Manager CEMVN-PM-OR 7400 Leake Avenue New Orleans, LA 70160 |
|
PROJECT STATUS REPORT as of 11-Jun-2026
Vermilion River Cutoff Bank Protection COMPLETE
PROJECT LOCATION:
PROJECT DESCRIPTION:
The revised project design includes protecting the east side of the Vermilion River Cutoff with rock to prevent further erosion; hardening the points on existing land bridges on the west bank of the Cutoff with rock; and constructing sediment trapping fences on the Vermilion Bay side to help stabilize and protect the land bridge from wave action in the Bay. The initial plan was revised when field investigations indicated that protection of the east bank of the Cutoff would best be accomplished with measures on the east bank; and that cutting off the west bank with a continuous dike would stop the flow of desirable nutrients and sediments from the Cutoff into Vermilion Bay through the breeches in the west bank land bridges.
PROJECT STATUS: (Project Status Last Updated: )
FUND STATUS:
The current project estimate is $2,023,685 , which includes $1,695,284 for construction first costs, and $117,404 and $210,997 for 20 years of monitoring and operations and maintenance, respectively.