COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 21-Oct-2019

Cameron-Creole Freshwater Introduction

PROJECT DATA

PROJECT: Cameron-Creole Freshwater Introduction
PRIORITY LIST: 18 PROJECT NO: 1801 CWPPRA NO: CS-49 DNR NO: CS-49
PROJECT TYPE: Freshwater Diversion NET ACRES BENEFITTED: 218
REGION: 4 BASIN: Calcasieu/Sabine PARISH: Cameron
LEAD AGENCY: NRCS
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA

MILESTONES:

CSA EXECUTION: 4-May-2009 ( Actual )    
DESIGN COMPLETION: 1-Nov-2014 *    
CONSTRUCTION START: 4-Apr-2012 ( Actual )    
CONSTRUCTION COMPLETION: 1-Jul-2016 *    
ESCROW AMENDMENT No:
MONITORING PLAN APPROVAL:    
O and M PLAN APPROVAL:    
DEAUTHORIZATION DATE:      
CASH FLOW PROECTS:        
Phase 1 Approval: 1/21/2009 ( Actual )    
Phase 2 Approval: 20-Jan-2010 ( Actual )    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT: 3 Charles W. Boustany
STATE SENATE DISTRICT: 999 Not Available
STATE HOUSE DISTRICT: 999 Not Available

Point of Contact:






,  
PHONES:  
Office:
Fax:

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 21-Oct-2019

Cameron-Creole Freshwater Introduction

PROJECT LOCATION:

PROJECT DESCRIPTION:


PROJECT STATUS: (Project Status Last Updated: 28-Nov-2016 )

Milestones shown above are for the vegetative component of the project only. Federal Sponsor does not have access to change the information relative to the structural components. Scheduled Dates: Phase II approval January 2018; Contracting April 2018; Construction Start September 2018

FUND STATUS:

The current project estimate is $21,171,677 , which includes $20,347,030 for construction first costs, and $104,577 and $720,070 for 20 years of monitoring and operations and maintenance, respectively.

LaCoast.gov Project Managers' Technical Factsheet