COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 6-Dec-2019

Raccoon Island Shoreline Protection/Marsh Creation

PROJECT DATA

PROJECT: Raccoon Island Shoreline Protection/Marsh Creation
PRIORITY LIST: 11 PROJECT NO: 1114 CWPPRA NO: TE-14-2 DNR NO: TE-48
PROJECT TYPE: Barrier Island NET ACRES BENEFITTED: 71
REGION: 3 BASIN: Terrebonne PARISH: Terrebonne
LEAD AGENCY: NRCS
LOCAL SPONSOR: DEPT. OF NATURAL RESOURCES, STATE OF LA

MILESTONES:

CSA EXECUTION: 23-Apr-2002 ( Actual )    
DESIGN COMPLETION: 1-Dec-2008 *    
CONSTRUCTION START: 13-Dec-2005 ( Actual )    
CONSTRUCTION COMPLETION: 27-Apr-2013 ( Actual )    
ESCROW AMENDMENT 27-Oct-2003 ( Actual ) No: 107
MONITORING PLAN APPROVAL:    
O and M PLAN APPROVAL:    
DEAUTHORIZATION DATE:      
CASH FLOW PROECTS:        
Phase 1 Approval: 1/16/2002 ( Actual )    
Phase 2 Approval: 13-Oct-2004 ( Actual )    

LEGISLATIVE DISTRICTS:

CONGRESSIONAL DISTRICT: 1 Steve Scalise
STATE SENATE DISTRICT: 20 Norby Chabert
STATE HOUSE DISTRICT: 53 Lenar L. Whitney

Point of Contact:






,  
PHONES:  
Office:
Fax:

COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT

PROJECT STATUS REPORT as of 6-Dec-2019

Raccoon Island Shoreline Protection/Marsh Creation

PROJECT LOCATION:

This project is located on Raccoon Island in Terrebonne Parish

PROJECT DESCRIPTION:

Eight segmented breakwaters will be installed along the gulf side of the island and dredged sediment will be used to create marsh on the land side of the island.

PROJECT STATUS: (Project Status Last Updated: 10-Dec-2014 )

Phase A construction began on 12/12/2005
Phase A construction ended on 9/16/2007

Phase B construction began on 9/27/2012
Phase B construction ended on 4/23/2103

FUND STATUS:

The current project estimate is $22,534,640 , which includes $19,250,895 for construction first costs, and $357,508 and $2,926,237 for 20 years of monitoring and operations and maintenance, respectively.