TABLE 10
CWPPRA restoration projects in the Pontchartrain Basin.
Restoration Objectives |
|||||||||
Projects |
Sponsor |
Project Type |
restore Fluvial Inputs |
Address MRGO Problems |
Prevent Marine Influence |
Address Imminent Loss |
Manage Existing Outfall |
Site- specific Marsh Loss |
Wetland Creation |
Fritchie Marsh (PO-6) |
NRCS |
HR |
|||||||
Violet Freshwater Distribution (PO-9A) |
NRCS |
HR |
|||||||
Bayou Sauvage Refuge Phase I (XPO-52A) |
USFWS |
HR |
|||||||
Bayou Sauvage Refuge Phase II (XPO-52B) |
USFWS |
HR |
|||||||
Bayou La Branche (PPO-10) |
USACE |
DM |
|||||||
MRGO Back Dike Marsh Protection (XPO-71) |
USACE |
MM |
|||||||
Eden Isles East Marsh Restoration (PPO-4) |
NMFS |
HR |
|||||||
Red Mud Coastal Restoration Demo. (XTE-43) |
EPA |
MC |
|||||||
Marsh Creation at Bayou Chevee (XPO-69) |
USACE |
DM |
HR = hydrologic restoration
DM = dredged material
MM = marsh management
MC = marsh creation