TABLE 9

Anticipated benefits and costs of CWPPRA restoration projects in the Atchafalaya River Delta Basin.

Projects

Total Created / Restored & Protected (acres)

Total Fully funded Cost Estimate

Atchafalaya Sediment Delivery (PAT-2)

2,232

$924,599

Big Island Mining (XAT-7)

1,560

$4,153,617

Atchafalaya River Delta Basin Total

3,792

$5,078,216